Saturday Work - 10/2/2021
The project will be working on the site this Saturday 10/2/2021. Activiteis will consist of the following:
- Millwork contractor will be working on punchlist items and clean up.
- Painting contractor will be painting stair #3 and working on punchlist items.
- Landscape contractor will be installing exterior bollards.
- Window shade contractor will be installing the shades in the gynasium.
- The site contractor will be stripping of street sidewalk crossings.
- Waterproofing contractor will be working on punch list items and caulking of exterior sidewalks.
- The mechanical contractor will be continuing balancing activities.
This weekend work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.