Elbridge Gerry Elementary School

Project Update - Week of January 11th 2021

egschooladm egschooladm 0 21 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.    
  • Building waterproofing detailing & flashing activities shall continue on the East, North & South elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the South, East & North elevations of Areas B & C of the building.  
  • The metal window contractor shall continue the installation of storefronts on the West, East & North elevations of Areas A, B & C of the building. 
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Areas A & B.
  • Installation of in-wall blocking shall continue on the second level of Areas A & B. 
  • Sheetrocking tops of wall have commenced and will continue on the second level of Areas A & B.
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A & B. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will commence this week in the Kitchen on the first level of Area B.
  • Lay-out activities for walls shall continue on the first level of Area C.
  • Installation of handrails & guardrails on Stair #3 shall continue in Area C.
  • The temporary heaters and equipment have been hooked-up and will be in use starting this week.

Saturday Work - 01/09/21

egschooladm egschooladm 0 15 Article rating: No rating

The project will be working on the site this Saturday 01/09/21.  Activities will consist of the following:

  • Laborers will be working on the interior of building performing general cleaning and organizing tasks to support a work activity scheduled to commence on Monday 1/11.  No lifts or equipment will be utilized to support these efforts. 

The allowable work hours for Saturday is 8AM – 5PM.  

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of January 4th 2021

egschooladm egschooladm 0 18 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.    
  • Building waterproofing detailing & flashing activities shall continue on the East, North & South elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the South, East & North elevations of Areas B & C of the building.  
  • The metal window contractor shall continue the installation of windows & storefronts on the West & East elevation of Areas A & B of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B. 
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Area A & B.
  • Installation of in-wall blocking shall continue on the second level of Area A & B. 
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A & B. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A & B.
  • The temporary heaters and equipment will continue with hook-up and are scheduled to start-up for use the week of 1/4.

Project Update - Week of December 28th 2020

egschooladm egschooladm 0 30 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.
  • The site contractor is scheduling the trucking companies to behing hauling unused materials offsite this week and next.     
  • Building waterproofing activities shall continue on the East, North & South elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the West, East & North elevations of Areas A, B & C of the building.  
  • The metal window contractor shall continue the installation of windows & storefronts on the West & East elevation of Areas A & B of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B. 
  • Installation of mechanical piping insulation shall continue on the interior second level of Areas A & B.    
  • Interior metal framing shall continue on the interior second level of Areas A & B.  Installation of insulation on the exterior walls shall continue this week on this level.  
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Area A. 
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A.
  • The temporary heaters and equipment will continue with hook-up and are scheduled to start-up for use the week of 12/28.
  • The project site will not be working on Friday 1/1/21 due to the Holiday; work will recommence on Monday 1/4/21.

Project Update - Week of December 21st 2020

egschooladm egschooladm 0 47 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.
  • The site contractor is scheduling the trucking companies to behing hauling unused materials offsite this week and next.     
  • Building waterproofing activities shall continue on the West, East & North elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the West, East & North elevations of Areas A, B & C of the building.  
  • The metal window contractor shall continue the installation of windows & storefronts on the West & East elevation of Areas A & B of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B. 
  • Installation of mechanical piping insulation shall continue on the interior second level of Areas A & B.    
  • Interior metal framing shall continue on the interior second level of Areas A & B.  Installation of insulation on the exterior walls shall continue this week on this level.  
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Area A. 
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A.
  • The temporary heaters and equipment were delivered and set-up on Wednesday 12/16.  Temporary barriers to protect the equipment are scheduled to arrive and be set on Tuesday 12/22.  The equipment will continue with hook-up and are scheduled to start-up for use the week of 12/28.
  • The project site will not be working on Friday 12/25 due to the Holiday; work will recommence on Monday 12/28.