The project will be working on the site this Saturday 8/21/21. Activities will consist of the following:
- Ceiling contractor will be installing speciality ceilings at the interior main lobby & corridor spaces.
- Millwork contractor will be prepping the radius millwork details at the Main Lobby and Bridge area.
- Flooring contractor will be continuing the install of flooring materials in the stage area and miscellanous rooms on the lower level of Area B/C. Installation of floor landings in Stair #3 will continue.
- Tel-Data contractor will be working on card reader installation in Area C.
- Painting contractor will be continuing with finish painting activites on the second/first floor corridor of Area A/B.
- Plumbing contractor will continue with final connections and finish in the Kitchen space.
- Specialities contractor will continue with installation of lockers on the second/first floor spaces.
- Site contractor will be setting curb along Dartmouth Road entrance and sub-grade prep for sidewalk to be ready for next week’s paving activity on Dartmouth Road. (Work to commence after 8am)
This weekend work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.