Lucretia and Joseph Brown Elementary School Project

Project Update - Week of January 4th 2021

egschooladm egschooladm 0 155 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.    
  • Building waterproofing detailing & flashing activities shall continue on the East, North & South elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the South, East & North elevations of Areas B & C of the building.  
  • The metal window contractor shall continue the installation of windows & storefronts on the West & East elevation of Areas A & B of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B. 
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Area A & B.
  • Installation of in-wall blocking shall continue on the second level of Area A & B. 
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A & B. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A & B.
  • The temporary heaters and equipment will continue with hook-up and are scheduled to start-up for use the week of 1/4.

Project Update - Week of December 28th 2020

egschooladm egschooladm 0 142 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.
  • The site contractor is scheduling the trucking companies to behing hauling unused materials offsite this week and next.     
  • Building waterproofing activities shall continue on the East, North & South elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the West, East & North elevations of Areas A, B & C of the building.  
  • The metal window contractor shall continue the installation of windows & storefronts on the West & East elevation of Areas A & B of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B. 
  • Installation of mechanical piping insulation shall continue on the interior second level of Areas A & B.    
  • Interior metal framing shall continue on the interior second level of Areas A & B.  Installation of insulation on the exterior walls shall continue this week on this level.  
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Area A. 
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A.
  • The temporary heaters and equipment will continue with hook-up and are scheduled to start-up for use the week of 12/28.
  • The project site will not be working on Friday 1/1/21 due to the Holiday; work will recommence on Monday 1/4/21.

Project Update - Week of December 21st 2020

egschooladm egschooladm 0 157 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.
  • The site contractor is scheduling the trucking companies to behing hauling unused materials offsite this week and next.     
  • Building waterproofing activities shall continue on the West, East & North elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the West, East & North elevations of Areas A, B & C of the building.  
  • The metal window contractor shall continue the installation of windows & storefronts on the West & East elevation of Areas A & B of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B. 
  • Installation of mechanical piping insulation shall continue on the interior second level of Areas A & B.    
  • Interior metal framing shall continue on the interior second level of Areas A & B.  Installation of insulation on the exterior walls shall continue this week on this level.  
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Area A. 
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A.
  • The temporary heaters and equipment were delivered and set-up on Wednesday 12/16.  Temporary barriers to protect the equipment are scheduled to arrive and be set on Tuesday 12/22.  The equipment will continue with hook-up and are scheduled to start-up for use the week of 12/28.
  • The project site will not be working on Friday 12/25 due to the Holiday; work will recommence on Monday 12/28.

Early Start for Snow Removal/Clean-Up - Friday 12/18/20

egschooladm egschooladm 0 162 Article rating: No rating

Due to the amount and period of time it snowed on Thursday the project will be bringing in a clean-up crew again on Friday 12/18 as a precautionary measure for the workers.  To support this effort the clean-up activites will commence at 5AM in advance of the trade workers arrival for the day.  This activity has been communicated to both the Marblehead Building Department and Police Department.

Project Update - Week of December 14th 2020

egschooladm egschooladm 0 146 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.
  • The site contractor is scheduling the trucking companies to behing hauling unused materials offsite this week and next.
  • The temporary heaters and equipment to provide heat in the building are scheduled to be delivered and set-up on Wednesday 12/16.  The equipment will commence hook-up on Thursday 12/17, note this activity may get pushed to Friday 12/18 due to the weather forecast.   
  • Building waterproofing activities shall continue on the West, East & North elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the West, East & North elevations of Areas A & B of the building.  
  • The metal window contractor shall continue the installation of windows on the West & East elevation of Area A of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B. 
  • Installation of mechanical piping insulation is scheduled to commence on the interior second level of Areas A & B.    
  • Interior metal framing shall continue on the interior second level of Areas A & B.  Installation of insulation on the exterior walls shall continue this week on this level.  
  • The mechanical contractor will continue lay-out and installing pipe and duct hangers on the first floor of Area A.
  • Rough-in of overhead mechanical duct and piping shall commence this week on the first floor of Area A. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A.

The weather forecast is predicting a snow event in this area for Thursday 12/17.  The project is currently scheduling snow plowing and clean-up crews to support a clear and safe site for the trade workers when they arrive to the project on Thursday morning.  To support this effort the snow plowing and clean-up activites will commence at 5AM in advance of the trade workers arrival for the day.  This activity has been communicated to both the Marblehead Building Department and Police Department.

    