The project will be working on the site this Saturday 4/24/21. Activities will consist of the following:
- Metal Window contractor will be working on the translucent panel installation on the exterior of Area C of the building . The work crew will be utilizing power tools and aerial lifts at times through out the day to support the work activities.
- General trades contractor will be working on sheetrocking activities on the first floor of Area C on the interior of the building.
- Ceiling contractor will working on ceiling grid installation on the first floor of Area A/B on the interior of the building.
This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.