The project will be working on the site this Saturday 5/8/21. Activities will consist of the following:
- Metal Window contractor will be working on the translucent panel installation on the exterior of Area C of the building . The work crew will be utilizing power tools and aerial lifts at times through out the day to support the work activities. This exterior work will not commence until 8AM.
- Electrical contractor will installing light fixtures in the classrooms on the second level of Area A/B in the building.
- General trades contractor will be working on sheetrocking activities in Area C of the building.
- Taping contractor will be working on taping and finishing sheetrocking activities on the first floor of Area C on the interior of the building.
This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.