Lucretia and Joseph Brown Elementary School Project

Saturday Work - 12/12/20

egschooladm egschooladm 0 187 Article rating: No rating

The project will be working on the site this Saturday 12/12/20.  Activities will consist of the following:

  • General Trades contractor will be working on interior lay-out activities and framing activities on the second floor of the building.  The work crew will be utilizing man-lifts and power tools (drills and saws) to support the work activities through out the day. 
  • Masonry contractor will be washing down the brick veneer on the South-East corner of the building.  The work crew will be utilizing the hydro-lift/staging and washing equipment to support the work activities.  The project is utilizing the warmer temperatures scheduled for Saturday to perform this weather sensitive activity.   

The allowable work hours for Saturday is 8AM – 5PM.  

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of December 7th 2020

egschooladm egschooladm 0 176 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with placing fill and subgrade prep along the East elevation of the project, adjacent to Gate B. 
  • The site contractor will continue with sub-grading activities on the West elevation of the site adjacent to Gate C/Dartmouth Road.  This area will be prepped and secured for the upcoming Winter months.  Due to the forecasted weather & temperatures the project will not place the asphalt binder in this area of the project site this season.
  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.  
  • The site contractor shall commence the excavation and installation of the drainage system & stone rip rap along the West elevation of the project site adjacent to the new parking lot and roadway on the property.    
  • Building waterproofing activities shall continue on the West, East & North elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the West, South & East elevations of Area A of the building. 
  • The metal window contractor shall commence the installation of windows on the West elevation of Area A of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B.     
  • Interior metal framing shall continue on the interior second level of Areas A & B.  
  • The mechanical contractor will continue lay-out and installing pipe and duct hangers on the first floor of Area A. 
  • The mechanical contractor is scheduled to receive deliveries of duct work for the first floor of Area A this week and commence rough-in of these materials.
  • Interior metal framing shall commence on the interior first level of Area A.    
  • The metal window contractor is scheduled to receive a delivery of metal windows & storefront glass on Monday 12/7 & Tuesday 12/8 of this week.  All materials will be offloaded and stored on the project site.  

Saturday Work - 12/5/20

egschooladm egschooladm 0 180 Article rating: No rating

The project will be working on the site this Saturday 12/12/20.  Activities will consist of the following:

  • General Trades contractor will be working on interior lay-out activities and framing activities on the second floor of the building.  The work crew will be utilizing man-lifts and power tools (drills and saws) to support the work activities through out the day. 
  • Masonry contractor will be washing down the brick veneer on the South-East corner of the building.  The work crew will be utilizing the hydro-lift/staging and washing equipment to support the work activities.  The project is utilizing the warmer temperatures scheduled for Saturday to perform this weather sensitive activity.   

The allowable work hours for Saturday is 8AM – 5PM.  

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of November 30th 2020

egschooladm egschooladm 0 176 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of the underground drainage system on the East side of the site, adjacent to Gate B of the project site.  Note this activity may require the use of a hammer drill at irregular intervals to break-up larger rocks/boulders and/or potential high spots of ledge that need to be taken down to support the drainage design. 
  • The site contractor will work on sub-grading activities on the West elevation of the site adjacent to Gate C/Dartmouth Road.  This is in preparation for placing asphalt binder before the plants close for the season.    
  • Building waterproofing activities shall continue on the West, East & North elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the West, South & East elevations of Area A of the building.   
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B.     
  • Interior metal framing shall continue on the interior second level of Area A.  
  • The mechanical contractor will continue lay-out on the first floor of Area A.
  • The metal window contractor is scheduled to receive two deliveries of the metal windows on Tuesday and Wednesday of this week.  Additionally a delivery of storefront glass is scheduled to be delivered on Thursday of this week.  All materials will be offloaded and stored on the project site.     

Project Update - Week of November 23rd 2020

egschooladm egschooladm 0 173 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of the underground drainage system on the East side of the site, adjacent to Gate B of the project site.  Note this activity may require the use of a hammer drill at irregular intervals to break-up larger rocks/boulders and/or potential high spots of ledge that need to be taken down to support the drainage design. 
  • The site contractor will work on sub-grading activities on the West elevation of the site adjacent to Gate C/Dartmouth Road.  This is in preparation for placing asphalt binder before the plants close for the season.   
  • Light gauge metal framing & sheathing activites on the exterior of the building shall continue on the South elevation of Area C on the building.  
  • Building waterproofing activities shall continue on the West, East & North elevations of Areas A & B on the building. 
  • The masonry contractor will continue working on the West, South & East elevations of Area A of the building.  This contractor will continue to receive the delivery of brick materials over the next three to four weeks; approx three deliveries of materials per week.  
  • Rough-in of overhead ductwork and piping shall continue on the interior second level of Areas A & B.     
  • Interior metal framing shall continue on the interior second level of Area A.  This contractor shall have a delivery of door frames for the first floor level on Monday 11/23.
  • The mechanical contractor will commence lay-out on the first floor of Area A this week.   
  • The project site will not be working on Thursday 11/26 in observation of the Thankgiving Holiday.  The project site will be working on Friday 11/27.  