Lucretia and Joseph Brown Elementary School Project

Saturday Work - 3/13/21

egschooladm egschooladm 0 192 Article rating: No rating

The project will be working on the site this Saturday 3/13/21.  Activities will consist of the following:

  • General Trades contractor will be working on sheetrocking activites on the first floor of the building.  The work crew will be utilizing power tools and scissor lift at times through out the day to support the work activities.
  • Painting contractor will be working on prime painting activities on the second floor of the building.  
  • Electrical contractor will be working in the main electrical room on rough-in and connections at the switchgear equipment. 

 

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of March 8th 2021

egschooladm egschooladm 0 237 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal window contractor shall continue the installation of storefronts & glazing installation on first level of the West & East elevations of Area A of the building.
  • The metal panel contractor will continue with installation of the fiber cement panels on the West & East elevation of the building.     
  • Production sheetrocking activities shall continue in the corridor spaces on the second level of Areas A & B.
  • Sheetrocking taping & sanding activities will continue on the second level of Areas A & B. 
  • Prime painting activities will continue in the Classroom spaces on the second level of Areas A & B.
  • Sheet rocking the top of wall activities will continue and production sheet rocking activities will continue on the first level of Areas A & B.
  • The project will receive sheet rock and support material deliveries this entire week for the first and second levels of Area A & B.
  • Installation of mechanical insulation activites shall continue on the first floor of Area A & B.
  • Light gauge metal framing activities in the Kitchen area shall continue on the first floor of Area B.
  • Rough-in of mechanical piping, ductwork, electrical & plumbing shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • Electrical rough-in in the Main Electrical Room will continue this week.  The electrical switchgear was received and offloaded into the building last week.  The electrical contractor will set the equipment and beging the rough-in and termination effort to the equipment this week.
  • Marblehead Light and Department of Public Works will commence with the excavation and installation of the electrical/communication duct bank to support permanent power on the West side of the project site and continue into Dartmouth Road this week. 

Saturday Work - 03/06/21

egschooladm egschooladm 0 207 Article rating: No rating

The project will be working on the site this Saturday 3/6/21.  Activities will consist of the following:

  • General Trades contractor will be working on taping, sanding and finishing activites of the sheet rock walls on the second floor of the building.  The work crew will be utilizing a scissor lift at times through out the day to support the work activities. 

 

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of March 1st 2021

egschooladm egschooladm 0 221 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal window contractor shall continue the installation of storefronts & glazing installation on first level of the West & East elevations of Area A of the building.
  • The metal panel contractor will continue with installation of the fiber cement panels on the West & East elevation of the building.   
  • The roofing contractor will continue with equipment roof curb flashings on the main roof level & transition down to the canopy roof installation.  
  • Production sheetrocking activities shall continue in the Classrooms and remaining spaces on the second level of Areas A & B.
  • Sheetrocking taping & sanding activities will continue on the second level of Areas A & B. 
  • Prime painting activities will commence in the Classroom mock-up room and continue through the second level of Areas A & B.
  • Sheet rocking the top of wall activities will continue and production sheet rocking activities will commence on the first level of Areas A & B.
  • The project will receive sheet rock and support material deliveries this entire week for the first and second levels of Area A & B.
  • Installation of mechanical insulation activites shall continue on the first floor of Area A & B.
  • The misc metal contractor is erecting the steel supports for the overhead doors systems on the interior of the building.  
  • Rough-in of mechanical piping, ductwork, electrical & plumbing shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • Electrical rough-in in the Main Electrical Room will continue this week.  The electrical switchgear for the project is scheduled to ship on Monday 3/1 and tentatively be delivered to the project site on Wednesday 3/3.  The equipment will be offloaded and set into the Main Electrical room on the West elevation of the building. 

Project Update - Week of February 22nd 2021

egschooladm egschooladm 0 302 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal window contractor shall continue the installation of storefronts & glazing installation on the North & South elevations of Areas A & C of the building.
  • The metal panel contractor will continue with installation of the fiber cement panels on the West elevation of the building.   
  • The roofing contractor will continue with equipment roof curb & skylight flashings on the main roof level.  
  • Production sheetrocking activities shall continue in the Classrooms and remaining spaces on the second level of Areas A & B.
  • Sheetrocking taping & sanding activities will continue on the second level of Areas A & B. 
  • Prime painting activities will commence in the Classroom mock-up room and continue through the second level of Areas A & B this week.
  • In-wall inspections on the first floor of Area A & B with the electrical inspector is scheduled for Monday 2/22.  The Town Building inspectors is scheduled for Tuesday 2/23 of this week.  Sheet rocking activities for this area is scheduled to commence on Wednesday 2/24.
  • Installation of mechanical insulation activites shall continue on the first floor of Area A & B.
  • The concrete topping slab in the Kitchen is scheduled to be placed on Thursday 2/25.  
  • Rough-in of mechanical piping, ductwork, electrical & plumbing shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • Electrical rough-in and setting of electrical panel housings and transformers in the Main Electrical Room will  continue this week.
  • Testing of the storefront glazing systems was rescheduled to Thursday 2/25 on the West & East elevations of the building.  This is due to the recent weather and temperatures.