Lucretia and Joseph Brown Elementary School Project

egschooladm egschooladm
/ Categories: Construction

Saturday Work - 6/19/21

The project will be working on the site this Saturday 6/19/21. Activities will consist of the following: 

  • General Trades contractor will be working on sheetrocking in Area B/C. 
  • Taping contractor will be working on taping and finishing activites on Level 2 Area B. 
  • Ceiling contractor will be working on the main lobby ceiling installation as well as second level corridor. 
  • Electrical contractor will be terminating light fixtures and fire alarm devices in the corridors as well as wiring for exterior lighting. 
  • Millwork contractor will be continuing level 1 classroom casework installation. 

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department. 

Previous Article Project Update - Week of June 14, 2021
Next Article Project Update - Week of June 21st 2021
Print
2218 Rate this article:
No rating

Theme picker