Lucretia and Joseph Brown Elementary School Project

Saturday Work - 9/18/21

egschooladm egschooladm 0 16 Article rating: No rating

The project will be working on the site this Saturday 9/18/21.  Activities will consist of the following:

  • Flooring contractor will be continuing with floor seam welding in the corridors on the first floor of the building.
  • Painting contractor will be finish painting the Main Lobby and Entry area and punchlist items in Area A/B.
  • Waterproofing contractor will be caulking exterior sidewalk joints.
  • Plumbing contractor will prep and paint the gas main lines on the exterior of the building.
  • Window Shade contractor continue with installation of motorized shades in the cafeteria.

This weekend work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Revised Project Vehicle Parking Plan - 9/16, 9/20, 9/21

egschooladm egschooladm 0 26 Article rating: No rating

The project is currently scheduled to prep and final pave the project site over a three day period starting on Friday 9/17, Monday 9/20 and Tuesday 9/21.  To support these work activities project vehicles will need to park outside of the project limits in the surrounding neighborhood during this period of time.

The project has developed the attached parking logicstics plan to help illustrate the location and streets the project vehicles will be parking on during this period of time.  The project will have monitors in the neighborhood each morning to ensure this plan is being followed.

This plan has been communicated and approved by the Marblehead Police Department.  Please see attached logicstics plan by clicking the "Read More" button for further information.    

Project Update - Week of September 13th 2021

egschooladm egschooladm 0 13 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • Carpet installation is continuing & completing the walk-off entry mats in the vestibule and entry/exits points at the building.  Remaining wall base shall continue and complete this week. 
  • The painting contractor is continuing with final paint activities on the second and first levels of Area A/B.
  • The millwork contractor is completing the installation of the handrail caps at the stairwells in the Main Lobby.
  • Final cleaning activities will continue in the first floor corridors and Main Lobby in Area A/B and exterior windows.  
  • The ceiling contractor shall complete the installation of the specialty ceilings in the main entry vestibule.
  • The misc metals contractor is scheduled to complete the remaining stainless steel handrail at Stair #2 this week. 
  • Pre-testing of the fire alarm system is on-going.  The final fire alarm test and inspection with the Town's Fire Department is scheduled for Friday 9/17 at 10AM.
  • The final elevator inspection with the State is scheduled for Tuesday 9/14 after 4:00PM
  • Irrigation installation is continuing on the North side of the project site.  Installation of heads and testing of the system on the South elevation shall commence on Monday 9/13.  The first delivery of sod materials is scheduled to arrive on-site Wednesday 9/15 and will be offloaded through Gate D adjacent to Baldwin Road and Gate C adjacent to Dartmouth Road.  
  • Installation of chain link fencing is continuing on the North elevation of the project site. 
  • Sub-grade prep at the athletic field is continuing this week followed by the spreading of top-soil in this area.
  • Landscape site accessories have begun delivery to the site and will continue through the week.  Installation and setting of these items will continue through out the week. 
  • The site contractor shall commence with final cleaning of the roadways and parking areas on Thursday and Friday of this week.  This is support final paving activities scheduled for Monday 9/20 and Tuesday 9/21.  

Saturday Work - 9/11/21

egschooladm egschooladm 0 17 Article rating: No rating

The project will be working on the site this Saturday 9/11/21.  Activities will consist of the following:

  • Ceiling contractor will be installing speciality ceilings at the main entry vestibule.
  • Millwork contractor will be installing acoustic wall panels in the main lobby and cafeteria and complete wood handrail caps.
  • Flooring contractor will be complete the flooring in the cafeteria corridor, carpet installation in the Media Center and flooring materials at Stair #2.
  • Painting contractor will be painting the custodial room floor, finish painting the Main Lobby space and punchlist items in Area A/B.
  • Landscaping contractor will continue with speading and setting stone dust and mulch along the North elevation of the project site.  (Work to commence after 8AM).
  • Elevator contractor will be installing the flooring materials in the elevator cab.
  • Misc Metal contractor will be completing the handrails at Stair #2.
  • Wood flooring contractor continuing with gym line painting.

This weekend work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of September 6th 2021

egschooladm egschooladm 0 17 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • Resilient Flooring installation is continuing & completing in the corridor space adjacent to the cafeteria and gymnasium. 
  • The painting contractor is continuing with final paint activities on the second and first levels of Area A/B.
  • The millwork contractor is completing the installation of the handrail caps at the stairwells in all Areas and continuing with the installation of the acoustic wall panels in the main lobby and corridors. 
  • Final cleaning activities will continue in the second & first floor corridors in Area A/B.  
  • The ceiling contractor shall complete with the installation of the specialty ceilings in the main entry vestibule and Media Center ceiling system.  
  • The carpet installation in the Media Center will commence on Wednesday and complete this week.
  • Wood flooring contractor shall complete the line striping painting of the gym floor this week.  
  • Setting of the operable partitions at the Stage area shall be completed this week.
  • The misc metals contractor is scheduled to complete the remaining stainless steel handrail installation this week. 
  • Pre-testing of the fire alarm system shall commence Wednesday 9/8 and continue through the end of the week.  
  • Installation of the remaining vertical granite curb in the parking lot shall be installed this week. 
  • Irrigation installation will continue on the North side of the project site.  
  • Installation of chain link fencing is continuing on the North elevation of the project site. 
  • Sub-grade prep at the  athletic field shall commence this week followed by the spreading of top-soil in this area.
  • Landscape site accessories have begun delivery to the site and will continue through the week.  Installation and setting of these items will continue through out the week.  
  • First delivery of sod is scheduled for Thursday 9/9.  