Lucretia and Joseph Brown Elementary School Project

Project Update - March 2nd, 2020

egschooladm egschooladm 0 435 Article rating: No rating

Please see below project update for the Elbridge Gerry Elementary School:

  • Construction office trailers arrived onsite week of 2/24/20.  Trailer set-up and hook-up of utilities (Electrical, Water and Sewer) are on-going through the weeks of 3/2/20 and 3/9/20. 
  • Site Perimeter Construction fence & scrim is complete along Baldwin Road and construction entrances.  Perimeter fence inside of the project site is on-going the week of 3/2/20.
  • Erosion Control measures are in-progress and will be on-going the week of 3/2/20.
  • Temporary Pest & Rodent Control measures to be installed the week of 3/2/20.  
  • Existing items identified to be salvaged and saved have been collected onsite.  Project team will coordinate with the Town of Marblehead for transport and delivery of salvage items to designaged area the week of 3/9/20.
  • Abatement activites for the Lower Bell building was completed week of 2/24/20.
  • Disconnect of the main electrical feed to the Lower Bell building has been completed by Marblehead Light.
  • Demolition of the Lower Bell building is scheduled to commence the week of 3/2/20.
  • Abatement activities for the Upper Bell building are on-going through the weeks of 3/2/20 and 3/9/20.
  • Abatement and removal of the Upper Bell roof is scheduled to commence the week of 3/9/20
  • Disconnect of the main electrical feed to the Upper Bell building is scheduled for the week of 3/9/20 by Marblehead Light.      

Project Update - February 10th, 2020

egschooladm egschooladm 0 499 Article rating: No rating
Please see below project update for the Elbridge Gerry Elementary School:
  • Marblehead Water & Sewer installed temporary hydrant on the property to support temporary water needs for the project.
  • National Grid disconnected the natural gas service lines to the Upper and Lower Bell School buildings the week of 2/3/20.
  • Project team coordinating with National Grid to coordinate and schedule remaining gas main cut & cap in Baldwin Road.  
  • Site Perimeter Construction fence & scrim tentatively scheduled to commence week of 2/17/20.
  • Erosion Control measures scheduled to commence week of 2/24/20.
  • Selective site demolition and stone pad area to support CM & OPM Trailers following the completion of construction fence & erosion control measures.

Neighborhood Meeting

egschooladm egschooladm 0 384 Article rating: No rating

On behalf of the Bell-Coffin-Gerry Building Committee and the Project Team, we are excited to invite you to attend a Project Update Meeting.

Our goal at the meeting is to provide you with a comprehensive update on the status of the New Elementary School project and what to expect moving forward. We look forward to introducing you to our Construction Management team (Gilbane Building Company), who will share the anticipated construction schedule and also provide you with information on where you can access additional up-to-the-minute updates as the project moves forward.  

Please join us on January 13, 2020, at 7:00 PM at the Glover Elementary School. 