Lucretia and Joseph Brown Elementary School Project

Saturday Work - 5/8/21

egschooladm egschooladm 0 2046 Article rating: No rating

The project will be working on the site this Saturday 5/8/21.  Activities will consist of the following:

  • Metal Window contractor will be working on the translucent panel installation on the exterior of Area C of the building .  The work crew will be utilizing power tools and aerial lifts at times through out the day to support the work activities.  This exterior work will not commence until 8AM.
  • Electrical contractor will installing light fixtures in the classrooms on the second level of Area A/B in the building.
  • General trades contractor will be working on sheetrocking activities in Area C of the building.
  • Taping contractor will be working on taping and finishing sheetrocking activities on the first floor of Area C on the interior of the building.

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of May 3rd 2021

egschooladm egschooladm 0 2041 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal panel contractor will continue with installation of the standing seam panel assembly on the South & East elevations of the building.
  • The metal window contractor will continue with the installation of the translucent system on the South & East elevations of Area C and the skylight on the roof level of Area A/B.      
  • Installation of MEP related equipment and devices in the ceiling grid shall continue on the second level of Areas A & B.
  • Prime painting activities shall continue on the first level on Areas A & B.
  • Installation of ceiling grid shall continue on the first level on Areas A & B.
  • The elevator contractor is continuing with installation of the elevator system in Area B.
  • Production sheetrocking & taping activities in the Cafeteria & Gym areas will continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.  Insulation of piping activities will continue in this space.
  • Backfill and subgrade prep around the perimeter of the building will continue along the South & East elevation of the building.
  • Site clean-up and grading activities will continue on the North elevation of the building.
  • Site contractor will cut/cap and/or connect the sewer and drainage utilities at the intersection of Baldwin and Jane Road.  Coordination with Marblehead's Department of Public Works is on-going to support these work activities.  Note this activity may require the use of a hammer drill at irregular intervals to break-up potential  spots of ledge that need to be taken down to support the utility installation. Grading and sub-grade preparation in this same area will follow the completion of the utilities.
  • Marblehead Light Department is tentatively scheduled to set a new utility pole on the project site Thursday 5/6 or Friday 5/7.  Note this work activity is weather dependant.
  • The metal panel contractor is scheduled to receive the delivery of equipment screens to be installed on the roof level this week.

Saturday Work - 5/1/21

egschooladm egschooladm 0 2070 Article rating: No rating

The project will be working on the site this Saturday 5/1/21.  Activities will consist of the following:

  • Metal Window contractor will be working on the translucent panel installation on the exterior of Area C of the building .  The work crew will be utilizing power tools and aerial lifts at times through out the day to support the work activities.  This exterior work will not commence until 8AM.
  • Taping contractor will be working on taping and finishing sheetrocking activities on the first floor of Area C on the interior of the building.

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of April 26th 2021

egschooladm egschooladm 0 2040 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal panel contractor will continue with installation of the standing seam panel assembly on the North, South & East elevations of the building.
  • The metal window contractor will continue with the installation of the translucent wall panel system on the South & East elevations of Area C.      
  • Painting activities will continue on the second level of Areas A & B.
  • Installation of MEP related equipment and devices in the ceiling grid shall continue on the second level of Areas A & B.
  • Production sheet rocking activities will continue on the first level of Areas B.
  • Prime painting activities shall continue on the first level on Areas A & B.
  • Installation of ceiling grid shall continue on the first level on Areas A & B.
  • The elevator contractor is continuing with installation of the elevator system in Area B.
  • Rough-in of electrical shall be completed in the Kitchen to support the final inspection on Wednesday 4/28.  This will support production sheetrocking to commence in this area.
  • Production sheetrocking activities in the Cafeteria & Gym areas will continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.  Insulation of piping activities have commenced in this space.
  • Grading and drainage stone along the South elevation of the new parking lot will commence this week.
  • Backfill and subgrade prep around the perimeter of the building will continue along the East elevation of the building.
  • Site clean-up and grading activities will continue on the North elevation of the building.
  • Site contractor will cut/cap and/or connect the water, sewer and drainage utilities at the intersection of Baldwin and Jane Road.  Coordination with Marblehead's Department of Public Works is on-going to support these work activities.  Grading and sub-grade preparation in this same area will follow the completion of the utilities.
  • The project received the first delivery of vertical granite curb today 4/26.  Installation of the curbing will commence this week and will be focused at the perimeter of the building footprint to support future concrete sidewalk construction.           

Saturday Work - 04/24/21

egschooladm egschooladm 0 1975 Article rating: No rating

The project will be working on the site this Saturday 4/24/21.  Activities will consist of the following:

  • Metal Window contractor will be working on the translucent panel installation on the exterior of Area C of the building .  The work crew will be utilizing power tools and aerial lifts at times through out the day to support the work activities.
  • General trades contractor will be working on sheetrocking activities on the first floor of Area C on the interior of the building.
  • Ceiling contractor will working on ceiling grid installation on the first floor of Area A/B on the interior of the building.

 

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.