Lucretia and Joseph Brown Elementary School Project

Project Update - Week of February 8th 2021

egschooladm egschooladm 0 1144 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of underground drainage elements & site prep on the East elevation of the project site.  Note this activity may require the use of a hammer drill at irregular intervals to break-up larger rocks/boulders and/or potential high spots of ledge that need to be taken down to support the site design.     
  • Building waterproofing detailing & flashing activities shall work to complete the leave out at the temporary stair location on the North elevations of the building.
  • The masonry contractor will complete the masonry veneer activities at the temporary stair location on the North elevation this week.  
  • The metal window contractor shall continue the installation of storefronts & glazing installation on the North & South elevations of Areas A & C of the building.
  • A delivery of exterior door frame systems are scheduled to arrive on-site Friday 2/12 and will be offloaded into the building.
  • The metal panel contractor will continue with installation of the fiber cement panel assembly on the East elevation of the building.   
  • The roofing contractor is tentatively scheduled to return to the site this week of 2/8/21.  Team to monitor the weather forecast for the week.  
  • The mechanical contractor is scheduled to receive a delivery of roof top equipment curbs on Monday 2/8.  The curbs will be hoisted via a crane and set on the roof level. 
  • Sheetrocking & Taping tops of walls will continue on the second level of Areas A & B.
  • Production sheetrocking activities shall continue in the Classrooms on the second level of Areas A & B.
  • Rough-in of overhead mechanical duct and piping shall continue on the first floor of Area A & B. 
  • In-wall rough-in of plumbing and electrical shall continue on first floor of Area A & B.
  • Installation of in-wall blocking shall continue on the first floor of Area A & B.
  • Installation of mechanical insulation activites shall commence on the first floor of Area A & B.
  • Backfill & concrete slab on grade prep will continue this week in the Kitchen on the first level of Area B.  The concrete slab placement is tentatively scheduled this week.  A concrete pump truck will be utilized to support the placement and will be located on the East elevation of the building adjacent to Gate B.
  • Rough-in of mechanical piping & ductwork shall continue on the first level of Area C.
  • Wall framing activities shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • Electrical rough-in and setting of electrical panel housings and transformers in the Main Electrical Room will commence this week.
  • Testing of the storefront glazing systems installed on the building is scheduled to occur commenced on Friday 2/12 on the West & East elevations of the building.

 

Early Start for Snow Removal/Clean-Up - Monday 2/8/21

egschooladm egschooladm 0 1150 Article rating: No rating

The weather forecast is calling for a snow event in this area for Sunday 2/7 into Monday 2/8.  The project is scheduling snow plowing and clean-up crews to support a clear and safe site for the trade workers when they arrive to the project site on Monday morning.  To support this effort the snow plowing and clean-up activities will commence at 5:00AM in advance of the trade workers arrival on site. 

Project Update - Week of February 1st 2021

egschooladm egschooladm 0 1129 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of underground drainage element and stone rip rap along the West elevation of the project site.    
  • Building waterproofing detailing & flashing activities shall work to complete the leave outs at the temporary stair locations on the South and North elevations of the building.
  • The masonry contractor will complete the masonry veneer activities at the temporary stair location on the South elevation this week.  This same work will continue this week at the North elevation of the building.
  • The metal window contractor shall continue the installation of storefronts & glazing installation on the West, East & North elevations of Areas A, B & C of the building.
  • The metal panel contractor will continue with installation of the fiber cement panel assembly on the West elevation of the building.   
  • The roofing contractor is tentatively scheduled to return to the site this week of 2/1/21.  Team to monitor the weather forecast for the week.   
  • Sheetrocking & Taping tops of walls will continue on the second level of Areas A & B.
  • Production sheetrocking activities shall commence this week in the Classrooms on the second level of Areas A & B.
  • Deliveries of sheetrock materials will continue through-out this week.  Expected deliveries for Wednesday & Friday of this week to support sheetrocking activities. 
  • Rough-in of overhead mechanical duct and piping shall continue on the first floor of Area A & B. 
  • In-wall rough-in of plumbing and electrical shall continue on first floor of Area A & B.
  • Installation of in-wall blocking shall continue on the first floor of Area A & B.
  • Installation of mechanical insulation activites shall commence on the first floor of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will continue this week in the Kitchen on the first level of Area B.  Plumbing inspection is scheduled for Wednesday 2/3, pending no issues backfill will commence followed by underground electrical rough-in.
  • Rough-in of mechanical piping & ductwork shall continue on the first level of Area C.
  • Wall framing activities shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will commence this week.
  • Electrical rough-in and setting of electrical panel housings and transformers in the Main Electrical Room will commence this week.
  • Testing of the metal windows installed on the building commenced today 2/1 on the West elevation of the building.

The weather forecast is predicting a snow event in this area for Tuesday 2/2 & Wednesday 2/3.  The project is currently scheduling snow plowing and clean-up crews to support a clear and safe site for the trade workers when they arrive to the project on Tuesday & Wednesday mornings.  To support this effort the snow plowing and clean-up activites will commence at 5:30AM in advance of the trade workers arrival for the day.&am

Project Update - Week of January 25th 2021

egschooladm egschooladm 0 1120 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of underground drainage element and stone rip rap along the West elevation of the project site.  
  • Building waterproofing detailing & flashing activities shall work to complete the leave outs at the temporary stair locations on the South and North elevations of the building.
  • The masonry contractor will follow the waterproofing contractor and complete the masonry veneer activities at the temporary stair location on the South elevations this week.  This same work will commence on Thursday of this week at the North elevation of the building.
  • The metal window contractor shall continue the installation of storefronts & glazing installation on the West, East & North elevations of Areas A, B & C of the building.
  • The metal panel contractor will continue with installation of the fiber cement panel assembly on the West elevation of the building.   
  • The roofing contractor is tentatively scheduled to return to the site the week of 2/1/21 due to forecasted weather temps for this week.
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Sheetrocking tops of walls will continue on the second level of Areas A & B.
  • The Town of Marblehead Building Inspector is scheduled to be onsite Tuesday 1/26 to inspect the in-wall activites on the second level of Area A & B. 
  • Deliveries of sheetrock materials will commence through-out this week.  These deliveries are to support the start of sheetrocking activities in the classrooms on the second level of Area A & B the week of 2/1/21.
  • Rough-in of overhead mechanical duct and piping shall continue on the first floor of Area A & B. 
  • In-wall rough-in of plumbing and electrical shall continue on first floor of Area A & B.
  • Installation of in-wall blocking shall commence on the first floor of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will continue this week in the Kitchen on the first level of Area B.
  • Rough-in of mechanical piping & ductwork shall continue on the first level of Area C.
  • Wall framing activities shall continue on the first level of Area C.
  • Delivery of water pumps located in the Mechanical Room were delivered and set in the building on Monday 1/25.  Piping rough-in and connections to the equipment will commence this week in the Mechanical Room.

Saturday Work - 01/23/21

egschooladm egschooladm 0 1146 Article rating: No rating

The project will have a service mechanic working on the site this Saturday 01/23/21.  This work was unforseen as the temporary heater located on the South end of the building broke-down this afternoon and the heat is needed to service the building through the weekend.  The service mechanic is scheduled for Saturday morning at 8AM in lieu of having the unit serviced Friday evening after the allowable work hours.  

This Saturday work has been communicated and coordinated with both the Marblehead Building Department & Police Department.