Lucretia and Joseph Brown Elementary School Project

Project Update - Week of March 1st 2021

egschooladm egschooladm 0 2057 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal window contractor shall continue the installation of storefronts & glazing installation on first level of the West & East elevations of Area A of the building.
  • The metal panel contractor will continue with installation of the fiber cement panels on the West & East elevation of the building.   
  • The roofing contractor will continue with equipment roof curb flashings on the main roof level & transition down to the canopy roof installation.  
  • Production sheetrocking activities shall continue in the Classrooms and remaining spaces on the second level of Areas A & B.
  • Sheetrocking taping & sanding activities will continue on the second level of Areas A & B. 
  • Prime painting activities will commence in the Classroom mock-up room and continue through the second level of Areas A & B.
  • Sheet rocking the top of wall activities will continue and production sheet rocking activities will commence on the first level of Areas A & B.
  • The project will receive sheet rock and support material deliveries this entire week for the first and second levels of Area A & B.
  • Installation of mechanical insulation activites shall continue on the first floor of Area A & B.
  • The misc metal contractor is erecting the steel supports for the overhead doors systems on the interior of the building.  
  • Rough-in of mechanical piping, ductwork, electrical & plumbing shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • Electrical rough-in in the Main Electrical Room will continue this week.  The electrical switchgear for the project is scheduled to ship on Monday 3/1 and tentatively be delivered to the project site on Wednesday 3/3.  The equipment will be offloaded and set into the Main Electrical room on the West elevation of the building. 

Project Update - Week of February 22nd 2021

egschooladm egschooladm 0 2186 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal window contractor shall continue the installation of storefronts & glazing installation on the North & South elevations of Areas A & C of the building.
  • The metal panel contractor will continue with installation of the fiber cement panels on the West elevation of the building.   
  • The roofing contractor will continue with equipment roof curb & skylight flashings on the main roof level.  
  • Production sheetrocking activities shall continue in the Classrooms and remaining spaces on the second level of Areas A & B.
  • Sheetrocking taping & sanding activities will continue on the second level of Areas A & B. 
  • Prime painting activities will commence in the Classroom mock-up room and continue through the second level of Areas A & B this week.
  • In-wall inspections on the first floor of Area A & B with the electrical inspector is scheduled for Monday 2/22.  The Town Building inspectors is scheduled for Tuesday 2/23 of this week.  Sheet rocking activities for this area is scheduled to commence on Wednesday 2/24.
  • Installation of mechanical insulation activites shall continue on the first floor of Area A & B.
  • The concrete topping slab in the Kitchen is scheduled to be placed on Thursday 2/25.  
  • Rough-in of mechanical piping, ductwork, electrical & plumbing shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • Electrical rough-in and setting of electrical panel housings and transformers in the Main Electrical Room will  continue this week.
  • Testing of the storefront glazing systems was rescheduled to Thursday 2/25 on the West & East elevations of the building.  This is due to the recent weather and temperatures.

Early Start for Snow Removal/Clean-Up - Tues 2/16/21 & Friday 2/19/21

egschooladm egschooladm 0 2065 Article rating: No rating

The weather forecast is predicting two separate snow/ice events in this area for Tues 2/16 & Friday 2/19.  The project will continue to monitor the forecast and schedule snow plowing and/or clean-up crews as needed to support a clear and safe site.  To support this effort the snow plowing and clean-up activities will commence at 5:00AM in advance of the trade workers arrival for the day on Tuesday and Friday.

Project Update - Week of February 15th 2021

egschooladm egschooladm 0 2066 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal window contractor shall continue the installation of storefronts & glazing installation on the North & South elevations of Areas A & C of the building.
  • A delivery of exterior door frame systems are scheduled to arrive on-site Friday 2/19 and will be offloaded into the building.
  • The metal panel contractor will continue with installation of the fiber cement panel assembly on the East & South elevations of the building.   
  • The roofing contractor will continue with equipment roof curb flashings on the main roof level. 
  • The mechanical contractor is scheduled to receive a delivery of roof top equipment curbs on Monday 2/8.  The curbs will be hoisted via a crane and set on the roof level. 
  • Production sheetrocking activities shall continue in the Classrooms and remaining spaces on the second level of Areas A & B.
  • Sheetrocking taping activities have commenced and will continue on the second level of Areas A & B. 
  • In-wall rough-in of plumbing and electrical shall continue on first floor of Area A & B.
  • Installation of in-wall blocking shall continue on the first floor of Area A & B.
  • In-wall inspections with applicable town inspectors are scheduled for this week on the first floor of Area A & B to support the start of sheet rocking activities the week of 2/22.
  • Installation of mechanical insulation activites shall continue on the first floor of Area A & B.
  • The concrete slab on grade placement for the Kitchen area is scheduled for Wednesday 2/17 this week.  A concrete pump truck will be utilized to support the placement and will be located on the East elevation of the building adjacent to Gate B.
  • Rough-in of mechanical piping & ductwork shall continue on the first level of Area C.
  • Wall framing activities shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • Electrical rough-in and setting of electrical panel housings and transformers in the Main Electrical Room will  continue this week.
  • Testing of the storefront glazing systems was rescheduled to Friday 2/19 on the West & East elevations of the building.

Early Start for Snow Removal/Clean-Up - Weds 2/10/21 & Friday 2/12/21

egschooladm egschooladm 0 2142 Article rating: No rating

The weather forecast is predicting two separate snow events in this area for Tues-Weds 2/9-2/10 & Friday 2/12.  The project will continue to monitor the forecast and schedule snow plowing and clean-up crews as needed to support a clear and safe site.  To support this effort the snow plowing and clean-up activities will commence at 5:00AM in advance of the trade workers arrival for the day on Wednesday and Friday.

RSS
First910111214161718Last

Theme picker