Lucretia and Joseph Brown Elementary School Project

Saturday Work - 01/23/21

egschooladm egschooladm 0 150 Article rating: No rating

The project will have a service mechanic working on the site this Saturday 01/23/21.  This work was unforseen as the temporary heater located on the South end of the building broke-down this afternoon and the heat is needed to service the building through the weekend.  The service mechanic is scheduled for Saturday morning at 8AM in lieu of having the unit serviced Friday evening after the allowable work hours.  

‚ÄčThis Saturday work has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of January 18th 2021

egschooladm egschooladm 0 170 Article rating: 5.0

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of underground drainage element and stone rip rap along the West elevation of the project site.  
  • Building waterproofing detailing & flashing activities shall work to complete the leave outs at the temporary stair locations on the South and North elevations of the building.   
  • The masonry contractor will follow the waterproofing contractor and commence the masonry veneer activities on the South and North elevations.
  • The metal window contractor shall continue the installation of storefronts & glazing installation on the West, East & North elevations of Areas A, B & C of the building.
  • The metal panel contractor has mobilized onsite to sruvey and layout.  Materials will be delivered on Monday, Thursday and Friday with installation of materials to commence the week of 1/25.  
  • The roofing contractor is scheduled to return to the site to complete detail and tie in work on Area C.  Note this work is weather and temperature dependant.
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Rough-in of in-wall electrical shall continue on the second level of Areas A & B.  Electrical inspection with the Town Inspector is scheduled for Thursday 1/21.
  • Installation of in-wall blocking shall be completed on the second level of Areas A & B. 
  • Sheetrocking tops of walls will continue on the second level of Areas A & B.
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A & B. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will continue this week in the Kitchen on the first level of Area B.
  • Lay-out activities for walls shall continue on the first level of Area C.  Wall framing activities shall commence this week on this level.
  • Rough-in of mechanical piping has commenced on the first level of Area C.
  • Concrete placement for Stairs #1, #3 and the equipment pads located in the mechanical room is scheduled for Wednesday 1/20.  Concrete pump truck is scheduled to arrive onsite at 7AM to begin set-up for the placements.  

Project Update - Week of January 11th 2021

egschooladm egschooladm 0 178 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.    
  • Building waterproofing detailing & flashing activities shall continue on the East, North & South elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the South, East & North elevations of Areas B & C of the building.  
  • The metal window contractor shall continue the installation of storefronts on the West, East & North elevations of Areas A, B & C of the building. 
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Areas A & B.
  • Installation of in-wall blocking shall continue on the second level of Areas A & B. 
  • Sheetrocking tops of wall have commenced and will continue on the second level of Areas A & B.
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A & B. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will commence this week in the Kitchen on the first level of Area B.
  • Lay-out activities for walls shall continue on the first level of Area C.
  • Installation of handrails & guardrails on Stair #3 shall continue in Area C.
  • The temporary heaters and equipment have been hooked-up and will be in use starting this week.

Saturday Work - 01/09/21

egschooladm egschooladm 0 181 Article rating: No rating

The project will be working on the site this Saturday 01/09/21.  Activities will consist of the following:

  • Laborers will be working on the interior of building performing general cleaning and organizing tasks to support a work activity scheduled to commence on Monday 1/11.  No lifts or equipment will be utilized to support these efforts. 

The allowable work hours for Saturday is 8AM – 5PM.  

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of January 4th 2021

egschooladm egschooladm 0 175 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.    
  • Building waterproofing detailing & flashing activities shall continue on the East, North & South elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the South, East & North elevations of Areas B & C of the building.  
  • The metal window contractor shall continue the installation of windows & storefronts on the West & East elevation of Areas A & B of the building. 
  • Rough-in of overhead mechanical, electrical, fire protection and plumbing shall continue on the interior second level of Areas A & B. 
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Area A & B.
  • Installation of in-wall blocking shall continue on the second level of Area A & B. 
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A & B. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A & B.
  • The temporary heaters and equipment will continue with hook-up and are scheduled to start-up for use the week of 1/4.