Lucretia and Joseph Brown Elementary School Project

Project Update - Week of April 26th 2021

egschooladm egschooladm 0 59 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal panel contractor will continue with installation of the standing seam panel assembly on the North, South & East elevations of the building.
  • The metal window contractor will continue with the installation of the translucent wall panel system on the South & East elevations of Area C.      
  • Painting activities will continue on the second level of Areas A & B.
  • Installation of MEP related equipment and devices in the ceiling grid shall continue on the second level of Areas A & B.
  • Production sheet rocking activities will continue on the first level of Areas B.
  • Prime painting activities shall continue on the first level on Areas A & B.
  • Installation of ceiling grid shall continue on the first level on Areas A & B.
  • The elevator contractor is continuing with installation of the elevator system in Area B.
  • Rough-in of electrical shall be completed in the Kitchen to support the final inspection on Wednesday 4/28.  This will support production sheetrocking to commence in this area.
  • Production sheetrocking activities in the Cafeteria & Gym areas will continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.  Insulation of piping activities have commenced in this space.
  • Grading and drainage stone along the South elevation of the new parking lot will commence this week.
  • Backfill and subgrade prep around the perimeter of the building will continue along the East elevation of the building.
  • Site clean-up and grading activities will continue on the North elevation of the building.
  • Site contractor will cut/cap and/or connect the water, sewer and drainage utilities at the intersection of Baldwin and Jane Road.  Coordination with Marblehead's Department of Public Works is on-going to support these work activities.  Grading and sub-grade preparation in this same area will follow the completion of the utilities.
  • The project received the first delivery of vertical granite curb today 4/26.  Installation of the curbing will commence this week and will be focused at the perimeter of the building footprint to support future concrete sidewalk construction.           

Saturday Work - 04/24/21

egschooladm egschooladm 0 61 Article rating: No rating

The project will be working on the site this Saturday 4/24/21.  Activities will consist of the following:

  • Metal Window contractor will be working on the translucent panel installation on the exterior of Area C of the building .  The work crew will be utilizing power tools and aerial lifts at times through out the day to support the work activities.
  • General trades contractor will be working on sheetrocking activities on the first floor of Area C on the interior of the building.
  • Ceiling contractor will working on ceiling grid installation on the first floor of Area A/B on the interior of the building.

 

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of April 19th 2021

egschooladm egschooladm 0 65 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal panel contractor will continue with installation of the standing seam panel assembly on the West, South & East elevations of the building.
  • The metal window contractor will continue with the installation of the translucent wall panel system on the South & East elevations of Area C.      
  • Painting activities will continue on the second level of Areas A & B.
  • Installation of ceiling grid shall continue on the second level of Areas A & B.
  • Installation of MEP related equipment and devices in the ceiling grid shall continue in the Classroom spaces on the second level of Areas A & B.
  • Production sheet rocking activities will continue on the first level of Areas A & B.
  • Prime painting activities shall continue on the first level on Areas A & B.
  • Installation of ceiling grid shall continue on the first level on Areas A & B.
  • The overhead hoods located in the Kitchen space are scheduled to be delivered and commence installation on Wednesday 4/21.
  • The elevator contractor is scheduled to mobilize and commence installation of the elevator system on Tuesday 4/20.  
  • Rough-in of electrical shall continue in the Cafeteria on the first level of Area C.
  • In-wall inspections are scheduled for Tuesday in the Cafeteria & Gym areas which will allow sheetrocking activities to commence in this space.
  • Sheetrocking activities in the Cafeteria & Gym areas will commence on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • Installation of remaining light pole bases along the South elevation of the parking lot will continue this week.  Grading and drainage stone along this same elevation will follow the installation of the light pole bases.
  • Backfill and subgrade prep around the perimeter of the building will continue along the West elevation of the building and continue on the South & East elevations.
  • Site clean-up and grading activities will commence on the North elevation of the building.  The temporary heater set-up located along this elevation is scheduled to be disconnected and removed on Thursday 4/22.
  • The project is scheduled to receive delivery of the metal panel enclosures located on the Roof Level this week.      

Saturday Work - 04/17/21

egschooladm egschooladm 0 68 Article rating: 5.0

The project will be working on the site this Saturday 4/17/21.  Activities will consist of the following:

  • Metal Window contractor will be working on installing skylight clips on the interior of the second floor of the building.  The work crew will be utilizing power tools and scissor lifts at times through out the day to support the work activities.
  • Electrical contractor will be working on rough-in activities through-out the interior of the building.

 

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of April 12th 2021

egschooladm egschooladm 0 63 Article rating: 2.0

Please see below project update for the Marblehead Elementary School: 

  • The metal panel contractor will continue with installation of the standing seam panel assembly on the West, South & East elevations of the building.
  • The metal window contractor will continue with the installation of the translucent wall panel system on the South & East elevations of Area C.      
  • Prime painting activities will continue on the second level of Areas A & B.
  • Installation of ceiling grid shall continue on the second level of Areas A & B.
  • Installation of MEP related equipment and devices in the ceiling grid shall continue in the Classroom spaces on the second level of Areas A & B.
  • Production sheet rocking activities will continue on the first level of Areas A & B.
  • Prime painting activities have commenced on the first level on Areas A & B.
  • Installation of ceiling grid has commenced on the first level on Areas A & B.
  • In-wall inspections are scheduled for this week in the Kitchen area which will allow sheetrocking activities to commence in this space.
  • Rough-in of electrical shall continue in the Cafeteria on the first level of Area C.
  • Light gauge metal framing activities in the Cafeteria will continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will continue this week.
  • The site contractor shall continue the construction of the retaining walls at the Dartmouth Rd entrance/exit.
  • Installation of light pole bases along the West elevation roadway will commence this week.  
  • The mechanical contractor is tentatively scheduled to have a crane onsite this week to pick and set the remaining roof-top units on the roof level of Area A.  The crane will be set-up along the West elevation of the building.     
RSS
124678910Last

Theme picker