Lucretia and Joseph Brown Elementary School Project

Project Update - Week of June 7, 2021

egschooladm egschooladm 0 123 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal panel contractor shall complete the installation of the equipment screen panels located on the roof level this week. 
  • The metal window contractor will continue with the installation of the remaining storefronts systems.  Additionally this contractor is scheduled to receive the delivery of skylight framing materials on Tuesday 6/8 and the associated glass and glazing materials are scheduled to ship to the site this week.
  • Resilient Flooring installation is continuing in the classrooms on the second level of Areas A & B.
  • The millwork contractor is continuing installation of materials on second level of Area A & B.  This contractor has a material delivery tentatively scheduled for Monday, Tuesday and Wednesday of this week.
  • The misc metals contractor is scheduled to be onsite Wednesday 6/9 to install the ceiling support system at the extended learning spaces on the second level of Area A & B.  
  • The elevator contractor is continuing with installation of the elevator system in Area B.  
  • The tiling contractor will continue with the installation of ceramic wall tile in the corridors, single & group bathrooms on the second and first levels of Areas A & B.
  • The plumbing contractor shall continue with the installation and connection of the plumbing fixtures in the classrooms on the second level of Areas A & B.
  • Production taping activities in the Cafeteria will continue on the first level of Area C.
  • The ceiling contractor will continue laying out the speciality ceiling system in the cafeteria on the floor to transfer up to the ceiling.
  • The installation of the overhead doors and coiling grill install will continue this week.  Followed by the remaining sheetrock activities.
  • The wood flooring contractor is tentatively scheduled to have the wood flooring materials deliverd to the project site on Thursday 6/10.  
  • Site clean-up and grading activities will continue on the North elevation of the building.  Note this activity may require the use of a hammer drill at irregular intervals to break-up potential spots of ledge that need to be taken down to support this work activity.
  • The site contractor is scheduling trucking to remove excess materials offsite this week.  Potentially 3-6 trucks will be running continuously through out the work day supporting this activity.
  • Sub-grade prep for asphalt sidewalks shall continue on the North and East elevations of the site.
  • The concrete flatwork contractor is continuing with sidewalk forming and reinforcing.  A concrete placement has been rescheduled to Tuesday 6/8 along the East elevation & main entrance of the building.  This was placement was rescheduled due to potential weather.
  • The landscape contractor will be working on the North elevation with site and sub-grade prep along the basketball court & playground area and the playground areas on the South elevation.

Saturday Work - 6/5/21

egschooladm egschooladm 0 94 Article rating: No rating

The project will be working on the site this Saturday 6/5/21.  Activities will consist of the following:

  • Electrical contractor will be terminating light fixtures and rough-in work on first level of Area A/B in the building.
  • General trades contractor will be working on sheetrocking activities in the building.
  • Taping contractor will be working on taping and finishing sheetrocking activities on the second level of Area A/B and first floor of Area C on the interior of the building.
  • Ceiling contractor will installing ceiling grid on the first level Area A/B and permforming ceiling lay-out activites in the Cafeteria space.
  • Painting contractor will be painting the main lobby ceiling and areas in the gymnasium.
  • Millwork contractor will be receiving and unloading a casework delivery on the second floor of Area A/B.
  • Flooring contractor will be installing flooring materials on the second floor of Area A/B.

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of May 31st, 2021

egschooladm egschooladm 0 96 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal panel contractor to continue the installation of the equipment screen panels located on the roof level this week.
  • The metal window contractor will continue with the installation of the remaining storefronts on the North, West & South elevations.
  • Resilient Flooring installation is continuing in the classrooms on the second level of Areas A & B.
  • The millwork contractor is continuing installation of materials on second level of Area A & B.  This contractor has a material delivery tentatively scheduled for Thursday and Friday of this week.  
  • The painting contractor is scheduled to prep and paint the roof/ceiling deck in the Main Lobby atrium this week.
  • The elevator contractor is continuing with installation of the elevator system in Area B.  
  • The tiling contractor will continue with the installation of ceramic wall tile in the corridors, single & group bathrooms on the second and first levels of Areas A & B.
  • The plumbing contractor shall continue with the installation and connection of the plumbing fixtures in the single bathrooms and corridors on the second and first levels of Areas A & B.
  • The ceiling contractor will continue with the ceiling grid clouds in the extended learning spaces on the first level of Area A & B.
  • The general trades contractor will continue sheetrocking activities in Stair #1 and Stair #3 spaces this week. 
  • Production sheetrocking & taping activities in the Cafeteria & Gym areas will continue on the first level of Area C.
  • The ceiling contractor will be laying out the speciality ceiling system in the cafeteria on the floor to transfer up to the ceiling on Friday & Saturday of this week. 
  • The project is scheduled to receive and set the emergency generator located on the West side of the project site on Friday 6/4.
  • Site clean-up and grading activities will continue on the North elevation of the building.  Note this activity may require the use of a hammer drill at irregular intervals to break-up potential spots of ledge that need to be taken down to support this work activity.
  • The site contractor is scheduling trucking to remove excess materials offsite this week.  Potentially 3-6 trucks will be running continuously through out the work day supporting this activity.
  • Sub-grade prep for asphalt sidewalks shall commence on the West elevation of the site working North on the site.
  • The concrete flatwork contractor is continuing with sidewalk forming and reinforcing.  A concrete placement is scheduled for Friday 6/4 along the East elevation & main entrance of the building.
  • The landscape contractor will be working on the North elevation with site and sub-grade prep along the East elevation and basketball court area.
  • Marblehead Light Department will be onsite Wednesday 6/2 to install metering equipment in the building.  Their crews will be onsite for the day and will be working within the building and at the utility pole located on the corner of Cornell and Dartmouth Roads through-out the day.

Saturday Work - 5/29/21

egschooladm egschooladm 0 110 Article rating: No rating

The project will be working on the site this Saturday 5/29/21.  Activities will consist of the following:

  • Electrical contractor will be terminating light fixtures and rough-in work on first level of Area A/B in the building.
  • General trades contractor will be working on sheetrocking activities in Area C of the building.
  • Taping contractor will be working on taping and finishing sheetrocking activities on the second level of Area A/B and first floor of Area C on the interior of the building.
  • Landscaping contractor will continue with tree installation along the West elevation of the project site.  This work will not commence until 8AM.

This Saturday work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of May 24th, 2021

egschooladm egschooladm 0 107 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • The metal panel contractor will complete the installation of the standing seam panel assembly on the South elevation of the building.
  • The metal panel contractor to continue the installation of the equipment screen panels located on the roof level this week.
  • The metal window contractor will continue with the installation of the translucent skylight system on the roof level of Area A & B.  Additionally this contractor will complete the sunshades installation on the building.  
  • The metal window contractor is receiving the remaining storefront entry systems on Wednesday 5/26 and will commence installation on the North elevation.
  • Resilient Flooring installation is continuing in the classrooms on the second level of Areas A & B.
  • The project is scheduling the final above ceiling inspection and sign off with the Town inspectors for the second level of Area A & B the week of 6/1/21. This will support the installation of ceiling tiles the same week.
  • The millwork contractor commenced receiving materials this morning and will commence installation on second level of Area A & B.  
  • The painting contractor is scheduled to prep and paint the roof/ceiling deck in the Main Lobby atrium this week.
  • The elevator contractor is continuing with installation of the elevator system in Area B.  
  • The tiling contractor has commenced and will continue with the installation of ceramic floor and wall tile in the single & group bathrooms on the first level of Areas A & B.
  • The plumbing contractor shall continue with the installation and hook-up of the plumbing fixtures in the single bathrooms on the first level of Areas A & B.
  • The general trades contractor will commence sheetrocking activities in Stair #1 and Stair #3 spaces this week. 
  • Production sheetrocking & taping activities in the Cafeteria & Gym areas will continue on the first level of Area C.
  • Backfill, utilities and subgrade prep around the perimeter of the building will continue along the East & South elevations of the building.  
  • Site clean-up and grading activities will continue on the North elevation of the building.  Note this activity may require the use of a hammer drill at irregular intervals to break-up potential spots of ledge that need to be taken down to support this work activity.
  • The site contractor is scheduling trucking to remove excess materials offsite this week.  Potentially 3-6 trucks will be running continuously through out the work day supporting this activity.
  • The concrete flatwork contractor is continuing with sidewalk forming and reinforcing.  A concrete placement is scheduled for Wednesday 5/26 along the South and East elevations of the building.
  • The landscape contractor has mobilized to the project site.   They will working on the North elevation with site and sub-grade prep along the East elevation and basketball court area.
  • The landscape contractor has a tree and plant delivery scheduled for Thursday 5/27.  Installation shall commence along the West elevation and new parking lot area.