Lucretia and Joseph Brown Elementary School Project

Project Update - Week of February 1st 2021

egschooladm egschooladm 0 963 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of underground drainage element and stone rip rap along the West elevation of the project site.    
  • Building waterproofing detailing & flashing activities shall work to complete the leave outs at the temporary stair locations on the South and North elevations of the building.
  • The masonry contractor will complete the masonry veneer activities at the temporary stair location on the South elevation this week.  This same work will continue this week at the North elevation of the building.
  • The metal window contractor shall continue the installation of storefronts & glazing installation on the West, East & North elevations of Areas A, B & C of the building.
  • The metal panel contractor will continue with installation of the fiber cement panel assembly on the West elevation of the building.   
  • The roofing contractor is tentatively scheduled to return to the site this week of 2/1/21.  Team to monitor the weather forecast for the week.   
  • Sheetrocking & Taping tops of walls will continue on the second level of Areas A & B.
  • Production sheetrocking activities shall commence this week in the Classrooms on the second level of Areas A & B.
  • Deliveries of sheetrock materials will continue through-out this week.  Expected deliveries for Wednesday & Friday of this week to support sheetrocking activities. 
  • Rough-in of overhead mechanical duct and piping shall continue on the first floor of Area A & B. 
  • In-wall rough-in of plumbing and electrical shall continue on first floor of Area A & B.
  • Installation of in-wall blocking shall continue on the first floor of Area A & B.
  • Installation of mechanical insulation activites shall commence on the first floor of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will continue this week in the Kitchen on the first level of Area B.  Plumbing inspection is scheduled for Wednesday 2/3, pending no issues backfill will commence followed by underground electrical rough-in.
  • Rough-in of mechanical piping & ductwork shall continue on the first level of Area C.
  • Wall framing activities shall continue on the first level of Area C.
  • Piping rough-in and connections to the equipment located in the Mechanical Room will commence this week.
  • Electrical rough-in and setting of electrical panel housings and transformers in the Main Electrical Room will commence this week.
  • Testing of the metal windows installed on the building commenced today 2/1 on the West elevation of the building.

The weather forecast is predicting a snow event in this area for Tuesday 2/2 & Wednesday 2/3.  The project is currently scheduling snow plowing and clean-up crews to support a clear and safe site for the trade workers when they arrive to the project on Tuesday & Wednesday mornings.  To support this effort the snow plowing and clean-up activites will commence at 5:30AM in advance of the trade workers arrival for the day.&am

Project Update - Week of January 25th 2021

egschooladm egschooladm 0 955 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of underground drainage element and stone rip rap along the West elevation of the project site.  
  • Building waterproofing detailing & flashing activities shall work to complete the leave outs at the temporary stair locations on the South and North elevations of the building.
  • The masonry contractor will follow the waterproofing contractor and complete the masonry veneer activities at the temporary stair location on the South elevations this week.  This same work will commence on Thursday of this week at the North elevation of the building.
  • The metal window contractor shall continue the installation of storefronts & glazing installation on the West, East & North elevations of Areas A, B & C of the building.
  • The metal panel contractor will continue with installation of the fiber cement panel assembly on the West elevation of the building.   
  • The roofing contractor is tentatively scheduled to return to the site the week of 2/1/21 due to forecasted weather temps for this week.
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Sheetrocking tops of walls will continue on the second level of Areas A & B.
  • The Town of Marblehead Building Inspector is scheduled to be onsite Tuesday 1/26 to inspect the in-wall activites on the second level of Area A & B. 
  • Deliveries of sheetrock materials will commence through-out this week.  These deliveries are to support the start of sheetrocking activities in the classrooms on the second level of Area A & B the week of 2/1/21.
  • Rough-in of overhead mechanical duct and piping shall continue on the first floor of Area A & B. 
  • In-wall rough-in of plumbing and electrical shall continue on first floor of Area A & B.
  • Installation of in-wall blocking shall commence on the first floor of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will continue this week in the Kitchen on the first level of Area B.
  • Rough-in of mechanical piping & ductwork shall continue on the first level of Area C.
  • Wall framing activities shall continue on the first level of Area C.
  • Delivery of water pumps located in the Mechanical Room were delivered and set in the building on Monday 1/25.  Piping rough-in and connections to the equipment will commence this week in the Mechanical Room.

Saturday Work - 01/23/21

egschooladm egschooladm 0 967 Article rating: No rating

The project will have a service mechanic working on the site this Saturday 01/23/21.  This work was unforseen as the temporary heater located on the South end of the building broke-down this afternoon and the heat is needed to service the building through the weekend.  The service mechanic is scheduled for Saturday morning at 8AM in lieu of having the unit serviced Friday evening after the allowable work hours.  

This Saturday work has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of January 18th 2021

egschooladm egschooladm 0 1077 Article rating: 5.0

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the excavation and installation of underground drainage element and stone rip rap along the West elevation of the project site.  
  • Building waterproofing detailing & flashing activities shall work to complete the leave outs at the temporary stair locations on the South and North elevations of the building.   
  • The masonry contractor will follow the waterproofing contractor and commence the masonry veneer activities on the South and North elevations.
  • The metal window contractor shall continue the installation of storefronts & glazing installation on the West, East & North elevations of Areas A, B & C of the building.
  • The metal panel contractor has mobilized onsite to sruvey and layout.  Materials will be delivered on Monday, Thursday and Friday with installation of materials to commence the week of 1/25.  
  • The roofing contractor is scheduled to return to the site to complete detail and tie in work on Area C.  Note this work is weather and temperature dependant.
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Rough-in of in-wall electrical shall continue on the second level of Areas A & B.  Electrical inspection with the Town Inspector is scheduled for Thursday 1/21.
  • Installation of in-wall blocking shall be completed on the second level of Areas A & B. 
  • Sheetrocking tops of walls will continue on the second level of Areas A & B.
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A & B. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will continue this week in the Kitchen on the first level of Area B.
  • Lay-out activities for walls shall continue on the first level of Area C.  Wall framing activities shall commence this week on this level.
  • Rough-in of mechanical piping has commenced on the first level of Area C.
  • Concrete placement for Stairs #1, #3 and the equipment pads located in the mechanical room is scheduled for Wednesday 1/20.  Concrete pump truck is scheduled to arrive onsite at 7AM to begin set-up for the placements.  

Project Update - Week of January 11th 2021

egschooladm egschooladm 0 989 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • The site contractor will continue with the construction of the landscaping retaining wall on the North elevation of the project site.    
  • Building waterproofing detailing & flashing activities shall continue on the East, North & South elevations of Areas B & C on the building. 
  • The masonry contractor will continue working on the South, East & North elevations of Areas B & C of the building.  
  • The metal window contractor shall continue the installation of storefronts on the West, East & North elevations of Areas A, B & C of the building. 
  • Installation of mechanical duct & piping insulation shall continue on the interior second level of Areas A & B.    
  • Rough-in of in-wall plumbing and electrical shall continue on the second level of Areas A & B.
  • Installation of in-wall blocking shall continue on the second level of Areas A & B. 
  • Sheetrocking tops of wall have commenced and will continue on the second level of Areas A & B.
  • Rough-in of overhead mechanical duct and piping shall continue this week on the first floor of Area A & B. 
  • Interior metal framing & setting of door frames shall continue on the interior first level of Area A & B.
  • Excavation, sub-grade prep & underground plumbing rough-in will commence this week in the Kitchen on the first level of Area B.
  • Lay-out activities for walls shall continue on the first level of Area C.
  • Installation of handrails & guardrails on Stair #3 shall continue in Area C.
  • The temporary heaters and equipment have been hooked-up and will be in use starting this week.