Lucretia and Joseph Brown Elementary School Project

Saturday Work - 9/25/21

egschooladm egschooladm 0 1970 Article rating: No rating

The project will be working on the site this Saturday 9/25/21.  Activities will consist of the following:

  • Painting contractor will be finish painting the Entry Lobby and Cafeteria corridor and punchlist items in Area A/B.
  • Millwork contractor will be working on millwork revisions in the second and first floor corridors in Area A/B.
  • Balancing contractor will be completing the water balancing effort for the entire building.

This weekend work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of 9/20/21

egschooladm egschooladm 0 2034 Article rating: 1.2

Please see below project update for the Marblehead Elementary School: 

  • Remaining flooring wall base and misc flooring punchlist items shall complete this week. 
  • The painting contractor is continuing with final paint activities on the first levels of Area B & C.
  • The millwork contractor is staining and finishing all of the handrail caps in the corridors, stairwells and Main Lobby areas.
  • Final cleaning activities will continue in the Main Lobby, Kitchen and corridor spaces in Areas B & C.   
  • Water balancing activities will continue and complete this week for the building.
  • Irrigation installation is continuing on the North side of the project site.  The Sod deliveries will continue this week; Monday will offload from Baldwin Road to allow installation to continue at areas directly adjacent to Baldwin Road.   
  • Installation of chain link fencing at the Pre-K playground area located on the South elevation of the building shall commence on Wednesday 9/22.
  • Spreading top soil at the athletic field shall commence this week followed by the installation of sod materials.
  • The site contractor shall commence final paving on Monday 9/20 and complete Tuesday 9/21.  Project vehicle parking shall return to parking onsite Wednesday 9/22.
  • The project's final inspections are scheduled as follows; Plumbing-Monday 9/20, Electrical-Wednesday 9/22 and Building-Friday 9/24.    

Saturday Work - 9/18/21

egschooladm egschooladm 0 1961 Article rating: No rating

The project will be working on the site this Saturday 9/18/21.  Activities will consist of the following:

  • Flooring contractor will be continuing with floor seam welding in the corridors on the first floor of the building.
  • Painting contractor will be finish painting the Main Lobby and Entry area and punchlist items in Area A/B.
  • Waterproofing contractor will be caulking exterior sidewalk joints.
  • Plumbing contractor will prep and paint the gas main lines on the exterior of the building.
  • Window Shade contractor continue with installation of motorized shades in the cafeteria.

This weekend work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of September 13th 2021

egschooladm egschooladm 0 2005 Article rating: No rating

Please see below project update for the Marblehead Elementary School: 

  • Carpet installation is continuing & completing the walk-off entry mats in the vestibule and entry/exits points at the building.  Remaining wall base shall continue and complete this week. 
  • The painting contractor is continuing with final paint activities on the second and first levels of Area A/B.
  • The millwork contractor is completing the installation of the handrail caps at the stairwells in the Main Lobby.
  • Final cleaning activities will continue in the first floor corridors and Main Lobby in Area A/B and exterior windows.  
  • The ceiling contractor shall complete the installation of the specialty ceilings in the main entry vestibule.
  • The misc metals contractor is scheduled to complete the remaining stainless steel handrail at Stair #2 this week. 
  • Pre-testing of the fire alarm system is on-going.  The final fire alarm test and inspection with the Town's Fire Department is scheduled for Friday 9/17 at 10AM.
  • The final elevator inspection with the State is scheduled for Tuesday 9/14 after 4:00PM
  • Irrigation installation is continuing on the North side of the project site.  Installation of heads and testing of the system on the South elevation shall commence on Monday 9/13.  The first delivery of sod materials is scheduled to arrive on-site Wednesday 9/15 and will be offloaded through Gate D adjacent to Baldwin Road and Gate C adjacent to Dartmouth Road.  
  • Installation of chain link fencing is continuing on the North elevation of the project site. 
  • Sub-grade prep at the athletic field is continuing this week followed by the spreading of top-soil in this area.
  • Landscape site accessories have begun delivery to the site and will continue through the week.  Installation and setting of these items will continue through out the week. 
  • The site contractor shall commence with final cleaning of the roadways and parking areas on Thursday and Friday of this week.  This is support final paving activities scheduled for Monday 9/20 and Tuesday 9/21.  

Saturday Work - 9/11/21

egschooladm egschooladm 0 1938 Article rating: No rating

The project will be working on the site this Saturday 9/11/21.  Activities will consist of the following:

  • Ceiling contractor will be installing speciality ceilings at the main entry vestibule.
  • Millwork contractor will be installing acoustic wall panels in the main lobby and cafeteria and complete wood handrail caps.
  • Flooring contractor will be complete the flooring in the cafeteria corridor, carpet installation in the Media Center and flooring materials at Stair #2.
  • Painting contractor will be painting the custodial room floor, finish painting the Main Lobby space and punchlist items in Area A/B.
  • Landscaping contractor will continue with speading and setting stone dust and mulch along the North elevation of the project site.  (Work to commence after 8AM).
  • Elevator contractor will be installing the flooring materials in the elevator cab.
  • Misc Metal contractor will be completing the handrails at Stair #2.
  • Wood flooring contractor continuing with gym line painting.

This weekend work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

RSS
245678910Last

Theme picker