Please see below the ledge drilling and blasting schedule for the week of 4/27/20.
Monday 4/27/20:
- Drilling activities to continue.
Tuesday 4/28/20:
- Drilling activities to continue.
- Two Blast Events Scheduled:
- First Blast to occur between 10AM-12PM
- Second Blast to occur between 12PM-2PM
Wednesday 4/29/20:
- Drilling activities to continue.
Thursday 4/30/20:
- Drilling activities to continue.
- Two Blast Events Scheduled:
- First Blast to occur between 10AM-12PM
- Second Blast to occur between 12PM-2PM
Friday 5/1/20:
- Drilling activities to continue.
On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).
Please note the blasting signals have been posted on the project site fence at Gates A, B & C. The signals required to be used are as follows:
- WARNING SIGNAL: Three long whistles five minutes prior to blast signal.
- BLAST SIGNAL: Two whistles one minute prior to the shot/blast.
BLAST OCCURS
- ALL CLEAR SIGNAL: A prolonged whistle following the inspection of the blast area.
PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS AND DENSITY.