Lucretia and Joseph Brown Elementary School Project

Ledge Drilling & Blasting Schedule - Week of 5/4/20

egschooladm egschooladm 0 306 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 5/4/20.

Monday 5/4/20:

  • Drilling activities to continue.

 

Tuesday 5/5/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Wednesday 5/6/20:

  • Drilling activities to continue.

 

Thursday 5/7/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Friday 5/8/20:

  • Drilling activities to continue.

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

Ledge Drilling & Blasting Schedule - Week of 4/27/20

egschooladm egschooladm 0 315 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 4/27/20.

Monday 4/27/20:

  • Drilling activities to continue.

 

Tuesday 4/28/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM
    • Second Blast to occur between 12PM-2PM

 

Wednesday 4/29/20:

  • Drilling activities to continue.

 

Thursday 4/30/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM
    • Second Blast to occur between 12PM-2PM

 

Friday 5/1/20:

  • Drilling activities to continue.

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS AND DENSITY.

Ledge Drilling & Blasting Schedule - Week of 4/20/20

egschooladm egschooladm 0 351 Article rating: 3.0

Please see below the ledge drilling and blasting schedule for the week of 4/20/20.

Monday 4/20/20:

  • Holiday – No drilling or blasting activities to occur.

 

Tuesday 4/21/20:

  • Drilling activities to commence.
  • Rock profiling exercise to commence.

 

Wednesday 4/22/20:

  • Drilling activities to continue.
  • Rock profiling exercise to continue

 

Thursday 4/23/20:

  • Drilling activities to continue.

 

Friday 4/24/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM
    • Second Blast to occur between 12PM-2PM

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

 BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS AND DENSITY.

Project Update - April 14th, 2020

egschooladm egschooladm 0 328 Article rating: No rating

Please see below project update for the Elbridge Gerry Elementary School:

  • Selective demolition of the Upper Bell exterior wall systems are in progress was completed the week of 4/6/20. 
  • Demolition and removal of the Upper Bell foundation systems are in progress and is scheduled to be completed the week of 4/13/20. 
  • Site contractor to moblize equipment the week of 4/13/20.
  • Ledge/Rock Profiling activity with the site enable and blasting contractor is scheduled to commence the week of 4/13/20.
  • Drilling rock areas to support the first "test" blast is to commence the week of 4/21/20.
  • Line drilling of weathered rock areas to commence the week of 4/21/20.
  • The first "test" ledge blasting activity is tentatively scheduled for Friday 4/24/20.  This date is tentative until the drilling activities commence to understand the density of the rock onsite.   
  • Project team will post weekly drilling & blasting look ahead schedules outlining both activities for that particular week.    

Revised Street Parking on Baldwin Road - Week of 4/13/20

egschooladm egschooladm 0 255 Article rating: 4.0

Please see below the revised street parking plan on Baldwin Road for the Week of 4/13/20:

  • Due to the size of the equipment being delivered to the project to support sitework activities there will be No Parking on one side of Baldwin Road.  The side of the road with “even” number houses shall have No Parking for the time periods noted below.
  • The No Parking zone shall start at the intersection of Pleasant St (Rte 114) & Baldwin Rd and end at the intersection of Baldwin Rd & Jane Rd.  The equipment shall enter the project site through construction Gate B.
  • The No Parking periods shall be for the following:
    • Tuesday 4/14 – 8AM-3:30PM
    • Wednesday 4/15 – 8AM-3:30PM
    • Thursday 4/16 – 3AM-3:30PM
  • Due to the size and weight of the equipment scheduled to be delivered Thursday morning the Department of Transportation (DOT) regulations requires the piece of equipment to be transported between the hours of 3AM-7AM.  The delivery truck will enter the site with the equipment and be turned off.  The offloading of the equipment will not occur until 7AM.
  • No Parking signs will be posted along Baldwin Road on Monday 4/13.
  • This revised parking plan and early morning equipment delivery has been communicated and coordinated with the Marblehead Police Department.
RSS
First1415161718192123

Theme picker