Lucretia and Joseph Brown Elementary School Project

Revised Street Parking on Baldwin Road - Week of 4/13/20

egschooladm egschooladm 0 240 Article rating: 4.0

Please see below the revised street parking plan on Baldwin Road for the Week of 4/13/20:

  • Due to the size of the equipment being delivered to the project to support sitework activities there will be No Parking on one side of Baldwin Road.  The side of the road with “even” number houses shall have No Parking for the time periods noted below.
  • The No Parking zone shall start at the intersection of Pleasant St (Rte 114) & Baldwin Rd and end at the intersection of Baldwin Rd & Jane Rd.  The equipment shall enter the project site through construction Gate B.
  • The No Parking periods shall be for the following:
    • Tuesday 4/14 – 8AM-3:30PM
    • Wednesday 4/15 – 8AM-3:30PM
    • Thursday 4/16 – 3AM-3:30PM
  • Due to the size and weight of the equipment scheduled to be delivered Thursday morning the Department of Transportation (DOT) regulations requires the piece of equipment to be transported between the hours of 3AM-7AM.  The delivery truck will enter the site with the equipment and be turned off.  The offloading of the equipment will not occur until 7AM.
  • No Parking signs will be posted along Baldwin Road on Monday 4/13.
  • This revised parking plan and early morning equipment delivery has been communicated and coordinated with the Marblehead Police Department.

Project Update - April 6th, 2020

egschooladm egschooladm 0 278 Article rating: No rating

Please see below project update for the Elbridge Gerry Elementary School:

  • Abatement and removal of the Upper Bell roof was completed the week of 3/23/20.
  • Selective demolition of the Upper Bell exterior wall systems are in progress and will continue through the week of 4/6/20. 
  • Demolition and removal of the Upper Bell foundation systems are scheduled to commence the week of 4/6/20. 
  • Second & Third round of pre-blast inspection notices have been sent via certified mail the week of 3/30/20.  Notices have been sent to property owners within the state required circumferance and all direct abutters to the project site.
  • Pre-blast inspections commenced and were completed between 4/3-4/6/20 for the property owners that responded and scheduled accordingly with the inspection company.  
  • Ledge/Rock Profiling activity with the site enable and blasting contractor is scheduled to commence the week of 4/13/20.
  • Line drilling of weathered rock areas and to support the "test" blast is to commence the week of 4/13/20.
  • Project team is working towards scheduling the first "test" ledge blasting activity on or before 4/17/20.  This "test" blast is to confirm adherence to the blast design plan created by the blasting contractor and subsequently reviewed by the Local Fire Deparment Officials.      

Project Update - March 26th, 2020

egschooladm egschooladm 0 280 Article rating: No rating

Please see below project update for the Elbridge Gerry Elementary School:

  • Demolition and removal of the Lower Bell building was completed the week of 3/16/20. 
  • Interior Abatement activities for the Upper Bell building completed the week of 3/16/20.
  • Abatement and removal of the Upper Bell roof is in progress and will complete the week of 3/23/20.
  • Selective demolition of the Upper Bell exterior wall systems are in progress and will continue through the week of 4/6/20. 
  • Demolition and removal of the Upper Bell foundation systems are scheduled to commence the week of 4/6/20. 
  • Balance of the scheduled tree removal to be completed the week of 3/30/20.
  • First round of pre-blast inspection notices have been sent via certified mail on Tuesday 3/24/20.  Notices have been sent to property owners within the state required circumferance and all direct abutters to the project site. 
  • Mobilization of the Site Enable contractor to commence the week of 4/6/20.
  • Ledge/Rock Profiling activity to commence the week of 4/13/20.

Project Update - March 17th, 2020

egschooladm egschooladm 0 317 Article rating: No rating

Please see below project update for the Elbridge Gerry Elementary School:

  • Erosion Control measures have been completed onsite as required.
  • Temporary Pest & Rodent Control measures have been installed onsite.  
  • Existing items identified to be salvaged and saved have been transported and delivered to the designaged area within Town.
  • Demolition of the Lower Bell building commenced as scheduled the week of 3/2/20.  Demolition is to continue through the week of 3/16/20. 
  • Interior Abatement activities for the Upper Bell building are to continue through the week of 3/16/20.
  • Abatement and removal of the Upper Bell roof commenced the week of 3/9/20 and will continue through the week of 3/16/20.
  • Selective demolition of the Upper Bell exterior wall systems are scheduled to commence the week of 3/23/20.
  • Disconnect of the main electrical feed to the Upper Bell building was completed by Marblehead light on 3/9/20.  All existing utility poles on site scheduled to removed was completed by Marblehead Light at this time.  

Project Update - March 2nd, 2020

egschooladm egschooladm 0 343 Article rating: No rating

Please see below project update for the Elbridge Gerry Elementary School:

  • Construction office trailers arrived onsite week of 2/24/20.  Trailer set-up and hook-up of utilities (Electrical, Water and Sewer) are on-going through the weeks of 3/2/20 and 3/9/20. 
  • Site Perimeter Construction fence & scrim is complete along Baldwin Road and construction entrances.  Perimeter fence inside of the project site is on-going the week of 3/2/20.
  • Erosion Control measures are in-progress and will be on-going the week of 3/2/20.
  • Temporary Pest & Rodent Control measures to be installed the week of 3/2/20.  
  • Existing items identified to be salvaged and saved have been collected onsite.  Project team will coordinate with the Town of Marblehead for transport and delivery of salvage items to designaged area the week of 3/9/20.
  • Abatement activites for the Lower Bell building was completed week of 2/24/20.
  • Disconnect of the main electrical feed to the Lower Bell building has been completed by Marblehead Light.
  • Demolition of the Lower Bell building is scheduled to commence the week of 3/2/20.
  • Abatement activities for the Upper Bell building are on-going through the weeks of 3/2/20 and 3/9/20.
  • Abatement and removal of the Upper Bell roof is scheduled to commence the week of 3/9/20
  • Disconnect of the main electrical feed to the Upper Bell building is scheduled for the week of 3/9/20 by Marblehead Light.      