The ground improvement activities are scheduled to be completed Wednesday 6/24/20. The contractor will begin demobilizing the equipment Wednesday 6/24 and preparing it for transport on Thursday morning 6/25. Please see below detailed schedule of activites for these two days:
- Wednesday - 6/24/20
- Demobilize support equipment and materials.
- Once ground improvement activities have been completed that day the pier driving rig will be dismantled and loaded for transport. This is to support a pick-up and exit with the equipment on Thursday morning; there will not be any loading of equipment on Thursday morning.
- Thursday - 6/25/20
- Transport personnel & truck will be onsite by 5:30AM to hook-up to the trailer for transport. The transport truck will enter the project site via Gate B, hook-up to the trailer and exit the project via Gate C to West Shore Drive to Route 114.
This morning equipment departure has been communicated and coordinated with the Marblehead Police Department.