Lucretia and Joseph Brown Elementary School Project

REVISED Water Service Shutdown on Baldwin Road - June 5, 2020

egschooladm egschooladm 0 249 Article rating: No rating

The scheduled water shutdown for Thursday on Baldwin Road has to be rescheduled to Friday June 5, 2020.  This is due to an unidentified/unknown underground utility line found during todays excavation effort.  The work crew will continue to be  working in Baldwin Road on Thursday in preparation for the shutdown and connection activity on Friday.  The water shutdown will between the hours of 8AM-3PM pending no further issues during the work.     

This revised work schedule has been scheduled and coordinated with the Marblehead Water & Sewer Department.  Project team members went door to door providing a revised notice this afternoon to the affected properties.  

The following properties will be affected and not have water service during this time period:

  • 33 Baldwin Road
  • 37 Baldwin Road
  • 39 Baldwin Road
  • 41 Baldwin Road
  • 43 Baldwin Road

 

The following properties may be affected if the existing gate valve scheduled to be closed on Thursday does not function and a gate valve further down Baldwin Road needs to be utilized:

  • 34 Baldwin Road
  • 31 Baldwin Road
  • 29 Baldwin Road
  • 1 Arlyn Road
  • 2 Arlyn Road
  • 27 Baldwin Road
  • 25 Baldwin Road
  • 24 Baldwin Road
  • 23 Baldwin Road
  • 17 Baldwin Road
  • 15 Baldwin Road
  • 14 Baldwin Road

Water Service Shutdown on Baldwin Road - June 4, 2020

egschooladm egschooladm 0 252 Article rating: No rating

On Thursday June 4, 2020 there will be a water shutdown to allow the connection of the projects new water line and valves in Baldwin Road adjacent to Gate D.  The water shutdown will be between the hours of 9AM-5PM on Thursday.  The project team will be working to complete this work expeditiously to allow the water service to be reactivated as soon as possible.  To help limit the shutdown period the project will be excavating in Baldwin Road on Wednesday June 3, 2020 to unearth the existing line and make safe the trench overnight with road plates to support the installation on Thursday morning.

This work has been scheduled and coordinated with the Marblehead Water & Sewer Department.  A formal notice from the Water & Sewer Department reiterating this shutdown information will be provided to the affected properties.  

 

The following properties will be affected and not have water service during this time period:

  • 33 Baldwin Road
  • 37 Baldwin Road
  • 39 Baldwin Road
  • 41 Baldwin Road
  • 43 Baldwin Road

 

The following properties may be affected if the existing gate valve scheduled to be closed on Thursday does not function and a valve further down Baldwin Road needs to be utilized:

  • 34 Baldwin Road
  • 31 Baldwin Road
  • 29 Baldwin Road
  • 1 Arlyn Road
  • 2 Arlyn Road
  • 27 Baldwin Road
  • 25 Baldwin Road
  • 24 Baldwin Road
  • 23 Baldwin Road
  • 17 Baldwin Road
  • 15 Baldwin Road
  • 14 Baldwin Road

Ledge Drilling & Blasting Schedule - Week of 6/1/20

egschooladm egschooladm 0 243 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 6/1/20.

Monday 6/1/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Tuesday 6/2/20:

  • Drilling activities to continue.

 

Wednesday 6/3/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Thursday 6/4/20:

  • Drilling activities to continue.

 

Friday 6/5/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

Project Update - May 26th, 2020

egschooladm egschooladm 0 257 Article rating: No rating

Please see below project update for the Elbridge Gerry Elementary School:

  • Continue hauling the existing loam materials offsite.
  • Continue stripping and hauling of existing asphalt materials offsite. 
  • Continue with site prep and fills using onsite material at the South & West areas of the project site.    
  • Commence ledge crushing activities on the North end of the project site, adjacent to the wooded area.     
  • Site contractor will continue to support, stock pile and hauling of blasted and excavated rock onsite/offsite. 
  • Connection to the existing water main in Baldwin Road to be scheduled the week of 6/1/20.  This work will be scheduled with Marblehead Water & Sewer Department this week for proper & timely notification to the affected property owners as water availability will be affected for the day of the connection. 
  • Please see seperate post for this weeks ledge drilling & blasting schedule. 

Ledge Drilling & Blasting Schedule - Week of 5/25/20

egschooladm egschooladm 0 256 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 5/25/20.

Monday 5/25/20:

  • MEMORIAL DAY - NO WORK

 

Tuesday 5/26/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Wednesday 5/27/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Thursday 5/28/20:

  • Drilling activities to continue.

 

Friday 5/29/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

RSS
First1415161719212223

Theme picker