Lucretia and Joseph Brown Elementary School Project

Project Update - Week of September 14th 2020

egschooladm egschooladm 0 2076 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • Continue with site prep, fills and grading on the South end of the project site to support the construction of the new parking lot area.  The use of vibratory compaction equipment will be used throughout this work activity.
  • Continue with backfill activites of the building retaining wall on the North end of the project site. 
  • Continue with underground utilities on the West side of the site working North towards Gate C located at Dartmouth Road. 
  • The excavation for underground utilities within the building footprint shall continue in Area A & B of the building. 
  • Continue with slab on deck prep and reinforcing on the 2nd Level and Roof Level in Areas A, B & C of the building.  The project is scheduled to have two seperate concrete slab on deck placements on Tuesday 9/15 and Thursday 9/17.  See seperate post for detailed scheduled of these concrete activities.
  • The perimeter roof blocking on the Roof Level shall continue in Areas A/B of the building.  The project will receive deliveries of lumber materials to support this activity. 

Potential Extended Work Hours - Tuesday 9/15 & Thursday 9/17

egschooladm egschooladm 0 2078 Article rating: No rating

The project has two (2) concrete slab on deck placements scheduled for Tuesday 9/15 and Thursday 9/17 of this week.  The project has coordinated and reduced these placements sizes with the concrete contractor to help decrease the duration of these work activities.  It is very typical in the industry that concrete slab on deck and concrete on grade placements require extended work hours to properly complete the work activity. 

Below is the tentative schedule for both concrete placement days.  Note the below periods of time are tentative and subject to change based on concrete service, weather and other potential unforeseen issues.

 

6:30AM – Concrete Pump Truck Mobilizes Onsite

 

7:00AM – 12:30PM – Place & Pump Concrete to Floor & Roof Decks

  • Approximately (22) Concrete Trucks will be accessing the project site to support this concrete placement

 

12:30PM – 4:00PM – Commence Concrete Finishing Activities.

  • Gas powered finishing equipment will be utilized during this period.

 

4:00PM – 5:00PM – Third Party Quality Control – Flatness Testing

 

5:00PM – 6:00PM – Cover the Concrete Slab with Curing Paper

  • Temporary light towers may be required to safely light the work area during this time period

 

6:00PM – 8:00PM – Contingency Period for Potential Delays - Concrete Service, Weather Effecting Cure Times, Etc.

 

This work schedule has been communicated and coordinated with both the Marblehead Building Department & Police Department.

Project Update - Week of September 8th 2020

egschooladm egschooladm 0 2127 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • Continue with site prep, fills and grading on the South end of the project site to support the construction of the new parking lot area.  The use of vibratory compaction equipment will be used throughout this work activity. 
  • The decking and detailing activities on the structural steel frame to continue through this week.  This includes the welding of composite nelson studs on the elevated floors which requires a large generator to support the welding activity.
  • Continue with underground utilities on the West side of the site working North towards Gate C located at Dartmouth Road. 
  • Demobilization and trucking offsite of the remaining retaining wall forms will occur this week.  It will be 2-3 flat bed trailers supporting this effort.  
  • The excavation for underground utilities within the building footprint shall commence in Area A of the building.  The project will receive deliveries of piping materials to support this activity.
  • The slab on deck prep and reinforcing on the 2nd Level and Roof Level shall commence in Areas A/B of the building.  The project will receive deliveries of reinforcing bar and mesh materials to support this activity.
  • The perimeter roof blocking on the Roof Level shall commence in Areas A/B of the building.  The project will receive deliveries of lumber materials to support this activity.     

Project Update - Week of August 31st 2020

egschooladm egschooladm 0 2068 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • Continue with site prep, fills and grading on the South end of the project site to support the construction of the new parking lot area.  The use of vibratory compaction equipment will be used throughout this work activity. 
  • Complete the erection of structural steel.  The crane is scheduled to demobilize this week.
  • The decking and detailing activities on the structural steel frame to continue through this week.  This includes the welding of composite nelson studs on the elevated floors which requires a large generator to support the welding activity.
  • Continue foundation waterproofing on the building retaining wall on the North end of the building.  Backfill activities at this retaining wall location will follow and support the waterproofing effort. The use of vibratory compaction equipment will be used throughout this work activity. 
  • Continue with underground utilities on the West side of the site working North towards Gate C located at Dartmouth Road. 
  • Demobilization and trucking offsite of the remaining retaining wall forms will occur this week.  It will be 2-3 flat bed trailers supporting this effort.  
  • The roofing contractor is scheduling a crane to be onsite Friday of this week to begin loading materials up onto the roof deck.     

Project Update - Week of August 17th 2020

egschooladm egschooladm 0 2135 Article rating: No rating

Please see below project update for the Marblehead Elementary School:

  • Continue with site prep, fills and grading on the South end of the project site to support the construction of the new parking lot area.
  • Continue with excavation and prep for concrete foundations on the North end of the building footprint (Areas B&C).  Note this activity may require the use of a hammer drill at irregular intervals to break-up larger rocks/boulders and/or potential high spots of ledge that need to be taken down to support the foundation design.  
  • The first concrete foundation crew to continue with the shallow footing & wall construction in Areas B&C of the building.   
  • The second concrete foundation crew to continue with footing & wall construction of the retaining wall from the West to East end of the building footprint (Area B to C).
  • Continue with back-fill operations within the building footprint on the West side of the building (Area B) working East (Area C).  Back-fill materials are currently onsite and will be transported within the project fence line to the appropriate work areas.  The use of vibratory compaction equipment will be used throughout this work activity. 
  • There are five concrete placements tentatively scheduled for this week; Monday 8/17/20, Tuesday 8/18/20, Wednesday 8/19/20, Thursday 8/20/20 and Friday 8/21/20. 
  • Steel erection will continue in Area A and progress towards Area B.  
  • The delivery schedule for steel is currently set-up for a delivery each day, Monday - Thursday over a 4-5 week period currently.  Note this schedule is subject to change based on the erector's need for material onsite.     

Please see below the revised street parking plan on Baldwin & Smith Road for the Week of 8/17/20:

  • The structural steel roof joists are scheduled to be delivered to the project site on two seperate days the week of 8/17/20.  Due to the size of the materials being delivered to the project there will be designated No Parking areas along both sides of Baldwin & Smith Roads.  The project has created a site plan attached to this posting identifying the No Parking areas for the time periods noted below.  Click the "Read More" button at the bottom of this posting to view the site plan.
  • The No Parking periods shall be for the following:
    • Tuesday 8/18 – 7AM-3:00PM
    • Thursday 8/20 – 7AM-3:00PM
  • No Parking signs will be posted along Baldwin & Smith Roads on Monday 8/17.
  • The project has scheduled three (3) Police details to accompany the deliveries each day to assist with traffic management and lead the deliveries down Baldwin Road. 
  • This revised parking plan and material delivery has been communicated and coordinated with the Marblehead Police Department.