Lucretia and Joseph Brown Elementary School Project

Water Service Shutdown on Baldwin Road - June 4, 2020

egschooladm egschooladm 0 1981 Article rating: No rating

On Thursday June 4, 2020 there will be a water shutdown to allow the connection of the projects new water line and valves in Baldwin Road adjacent to Gate D.  The water shutdown will be between the hours of 9AM-5PM on Thursday.  The project team will be working to complete this work expeditiously to allow the water service to be reactivated as soon as possible.  To help limit the shutdown period the project will be excavating in Baldwin Road on Wednesday June 3, 2020 to unearth the existing line and make safe the trench overnight with road plates to support the installation on Thursday morning.

This work has been scheduled and coordinated with the Marblehead Water & Sewer Department.  A formal notice from the Water & Sewer Department reiterating this shutdown information will be provided to the affected properties.  

 

The following properties will be affected and not have water service during this time period:

  • 33 Baldwin Road
  • 37 Baldwin Road
  • 39 Baldwin Road
  • 41 Baldwin Road
  • 43 Baldwin Road

 

The following properties may be affected if the existing gate valve scheduled to be closed on Thursday does not function and a valve further down Baldwin Road needs to be utilized:

  • 34 Baldwin Road
  • 31 Baldwin Road
  • 29 Baldwin Road
  • 1 Arlyn Road
  • 2 Arlyn Road
  • 27 Baldwin Road
  • 25 Baldwin Road
  • 24 Baldwin Road
  • 23 Baldwin Road
  • 17 Baldwin Road
  • 15 Baldwin Road
  • 14 Baldwin Road

Ledge Drilling & Blasting Schedule - Week of 6/1/20

egschooladm egschooladm 0 1986 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 6/1/20.

Monday 6/1/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Tuesday 6/2/20:

  • Drilling activities to continue.

 

Wednesday 6/3/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Thursday 6/4/20:

  • Drilling activities to continue.

 

Friday 6/5/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

Project Update - May 26th, 2020

egschooladm egschooladm 0 1941 Article rating: No rating

Please see below project update for the Elbridge Gerry Elementary School:

  • Continue hauling the existing loam materials offsite.
  • Continue stripping and hauling of existing asphalt materials offsite. 
  • Continue with site prep and fills using onsite material at the South & West areas of the project site.    
  • Commence ledge crushing activities on the North end of the project site, adjacent to the wooded area.     
  • Site contractor will continue to support, stock pile and hauling of blasted and excavated rock onsite/offsite. 
  • Connection to the existing water main in Baldwin Road to be scheduled the week of 6/1/20.  This work will be scheduled with Marblehead Water & Sewer Department this week for proper & timely notification to the affected property owners as water availability will be affected for the day of the connection. 
  • Please see seperate post for this weeks ledge drilling & blasting schedule. 

Ledge Drilling & Blasting Schedule - Week of 5/25/20

egschooladm egschooladm 0 1922 Article rating: No rating

Please see below the ledge drilling and blasting schedule for the week of 5/25/20.

Monday 5/25/20:

  • MEMORIAL DAY - NO WORK

 

Tuesday 5/26/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Wednesday 5/27/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

Thursday 5/28/20:

  • Drilling activities to continue.

 

Friday 5/29/20:

  • Drilling activities to continue.
  • Two Blast Events Scheduled:
    • First Blast to occur between 10AM-12PM**
    • Second Blast to occur between 12PM-3PM**

 

On all scheduled blast days a representative from the Marblehead Fire Department will be onsite for the blast event(s).

 

Please note the blasting signals have been posted on the project site fence at Gates A, B & C.  The signals required to be used are as follows:

  1. WARNING SIGNAL:           Three long whistles five minutes prior to blast signal.
  2. BLAST SIGNAL:                  Two whistles one minute prior to the shot/blast.

                                                                            BLAST OCCURS

  1. ALL CLEAR SIGNAL:          A prolonged whistle following the inspection of the blast area.   

 

**PLEASE NOTE THIS SCHEDULE IS TENTATIVE AND SUBJECT TO CHANGE DUE TO THE LEDGE/ROCK CHARACTERISTICS, DENSITY AND WEATHER CONDITIONS.

Early Morning Equipment Delivery - May 22, 2020

egschooladm egschooladm 0 2055 Article rating: No rating

On Friday morning May 22, 2020 there will be a delivery of equipment between the hours of 5AM-6AM.  The delivery trucks with the equipment will enter the project site through Gate C located on Dartmouth Road and will be turned off.  The offloading of the equipment will not occur until 7AM. 

Due to the size and weight of the equipment scheduled to be delivered Friday morning the Department of Transportation (DOT) regulations requires the pieces of equipment to be transported between the hours of 3AM-7AM.  

This early morning equipment delivery has been communicated and coordinated with the Marblehead Police Department.

RSS
First2122232426282930

Theme picker